Task details pop-up
Contents: |
---|
Open the pop-up
A pop-up dialogue box appears when you click on a task from the Gantt chart.
Expand
Use the Expand button to maximize the pop-up.
Listed information
The following information is listed in the pop-up:
Task icon
Task key
Task summary
Progress
Status
Start date
End date
Period mode
In the scope of - displays all IDs of the boxes in which the task is (even if you can’t access these boxes)
Task ID
See changes
Opens the task history in the side panel. The filters are automatically active - only the selected task is listed in the results. To learn more, see the Change history page.
Note: To see the side panel, you must collapse the pop-up. The side panel is not visible when task details are expanded.
Inline editing
Inline editing is available in the task details pop-up. To learn more, see the Inline edit page.