Workload details

Workload

Click the Workload or Remaining capacity cells to display a dialog containing detailed information about all allocated workloads resulting from the tasks in a given period.

This detailed view works in time tracking (Original and Remaining estimate), and Story points effort modes. The dialog appears whenever you click any Workload or Remaining capacity cell within:

  • Individuals, Teams, Projects, or Skills swimlane

  • Summary lane

  • Unassigned lane

Screenshot of the Workload details pop-up window in the new view of the Resources module.

Aggregation

You can change the aggregation (daily, weekly, monthly, quarterly, yearly, by time boxes). To learn more, see the Scale: Time Period and Aggregation page.

Screenshot of the Aggregation menu in the new view of the Resources module.

Workload formula

The table in the dialog shows all tasks that contribute to the Total workload calculated using the following formula: Total workload = Sum of all estimates of the assigned tasks.

Workload values are presented in hours. The following rules apply:

  • If the task is overdue (the end date < current date), only the logged work (spent time) will be added to the total workload.

  • If the task has not started yet (the start date > current date), only the remaining estimate will be added to the total workload.

The workload details dialog displays tasks with workload = 0 to signal to inform that some tasks need estimation.

Actions on a dialog box

The table describes how to resize and expand a dialog box.

Action

Description

Action

Description

Resize

You can change the dialog box size to make working with workload details easier.

Expand

Click the Expand icon to see all workload details.