Workload details
Contents: |
---|
Workload
Click the Workload details or Remaining Capacity cells to display a dialog containing detailed information about all allocated workload resulting from the tasks in a given period.
You can change the aggregation (daily, weekly, monthly, by time boxes).
This detailed view works in Time tracking (Original and Remaining estimate) and Story points effort modes. The dialog appears whenever you click any Workload or Remaining capacity cell within:
individual resource lane
team resource lane
summary lane
unassigned lane.
Workload formula
The table in the dialog shows all tasks that contribute to the Total workload calculated using the following formula:
Total workload = Sum of all estimates of the assigned tasks.
Workload values are presented in hours
The following rules apply:
If the task is overdue (the end date < current date), only the Logged work (Spent time) will be added to the Total workload.
If the task has not started yet (the start date > current date), only the Remaining estimate will be added to the Total workload.
For example:
Angela is working full time (40h/w) and is assigned three tasks, but only BPV-21 and BPV-2 have time estimates. The Total workload during week 22 is 49.8h+8.6h=58.4h. As the weekly capacity is 40h, the Remaining capacity is 40h-58.4h=-18.6h
The workload details dialog displays tasks with workload = 0 to signal to the user that some tasks still need estimation.
Dialog box resizing
You can change the dialog box size to make working with workload details easier.
Expand to modal