Support for Atlassian Server Products (and apps like BigPicture) has ended in February 2024.

Are you planning a migration to Cloud? Make sure you don't lose your BigPicture data/configurations in the process. Check out this page for information on how to migrate BigPicture's data to Cloud. If you have any questions please email support@appfire.com

Overdue tasks

Introduction

An overdue task is one whose finish date is earlier than today and whose status is other than closed. You can see all work items that are running late in the Infobar.

Overdue tasks are sorted in descending order, with the most overdue tasks at the top of the list.

The overdue tasks feature works for:

  • Tasks that have start and end dates

     

  • Tasks that have only an end date (the task is semi-transparent)

The overdue tasks feature does NOT work for:

  • Tasks without start and end dates

  • Tasks with a start date, but no end date

Overdue task color coding

On the timeline, overdue tasks are red or yellow and include the number of days overdue:

  • Redoverdue > 7 days

  • Yellowoverdue  3 -7  days 

The tasks in grey are either completed on time or not running late.

Finding overdue tasks on the timeline

To find overdue tasks on the timeline, click anywhere on the task row. If you click on the issue key, you will open the detailed view in a new window.

Infobar

Overdue tasks can be displayed in a list form, in the Infobar: