Duplicate a box and scope

 

Duplicating a Box

You can create a new box by duplicating an existing box.

When you duplicate a box, the box configuration is copied. BigPictuer copies as much of the box setup as possible. Box type settings and defaults are ignored in favor of the exact setup of the Box you are making a copy of.

Steps

  1. Activate the actions menu

    1. by clicking on the three dots menu icon on the right OR

    2. by right-clicking on a box row

  2. Select Duplicate configuration. A box creation pop-up appears.

image-20241118-073335.png
  1. The following fields are pre-filled:

    • Type (can’t be changed)

    • Name

    • Icon

    • Start date

    • End date

    • Jira Projects (not required)

      • available only for project boxes (can’t be filled in for boxes without their own scope, such as portfolio). Box scope can be adjusted later in a box configuration.

    image-20241118-083232.png
  2. Click Create

What is duplicated

Settings

Result

Settings

Result

Box scope

Not copied.

The scope configuration is not copied.

Box content is not replicated (projects, tasks, issues etc). 

Sub boxes

Not copied

Child boxes are not duplicated.

Reports

Not copied

Existing reports are not duplicated.

Objectives

Not copied

Existing objectives are not duplicated.

Box settings

The following box settings are duplicated:

  • Modules - the list of active/inactive modules

  • Task structure

  • Scheduling

    • Task scheduling mode

    • Task scheduling mode per task type

    • Task period alignment

  • Workload contouring settings

  • Box roles

  • Column views and card views (for Overview, Gantt, Scope, Board, and Risks modules)

  • task templates

  • Baselines permissions settings

  • box lead

Box type settings

The following are the same for all boxes of a given type and can’t be modified for individual boxes:

  • Scope type

  • Sequentiality

  • Box period mode

  • Scheduling

  • Story points

  • Story point conversion ratio enabled/disabled

  • teams enabled (inherited and manually created)

Box type defaults and templates

When you duplicate a box, settings are duplicated directly from the box you are making a copy of. Box type templates are ignored.

Applies to:

  • Box roles

  • Column views and card views

  • Task templates

Default task templates are configured for the “LeSS Requirement Area” box type.

When a box is duplicated, default task templates of a box type are ignored. The actual task templates from a box are copied.

Inherited settings

Inherited settings are based on a position in a box tree and can’t be duplicated.

 


Clone Scope

Scope cloning creates duplicates of tasks. This action creates tasks in a box you are currently in.

Steps

  1. Configure the box scope - cloned issues will be added to a Jira project listed in scope definition.

  1. Click the + button (available in Gantt and Scope modules)

  2. Select Clone existing scope. A pop-up appears.

  1. Select:

    1. A box that contains tasks to be copied (source of tasks)

    2. A Jira project the duplicates will be created in (target project)

  1. Click Clone

 

Which data can be clonned

Data

Cloning result (Yes / No)

Data

Cloning result (Yes / No)

Jira issue

yes

Basic tasks

no

Issue types

if possible

When possible, the new issue has the same type as the one being copied.

  • Epics and sub-tasks are cloned as the default issue type. This means that after cloning, your new project doesn’t have any epics or sub-tasks.

  • If Jira setup allows, the new issues are cloned with the same issue type.

  • Otherwise, the default issue type is used.

Task structure

No

Structure builders aren’t cloned:

  • Epics and sub-tasks are cloned as the default issue type. Therefore, it is not possible for an epic-based structure to be automatically recreated.

  • The position of tasks manually moved can’t be recreated.

  • Basic tasks aren’t cloned. Therefore, task structure based on basic tasks can’t be recreated.

  • Versions, Components, and Sprints aren’t cloned and are not added to the target project during cloning. Therefore, the structure based on those elements cannot be automatically recreated.

Dependencies

yes

Summary

yes

Start / End date

yes

The position of tasks on the timeline is preserved.

Data is cloned according to field mapping.

Baseline start/end date

yes

Other fields besides Summary and synchronized date fields

no

Examples:

  • priority

  • assignee

  • labels

  • team

Skills

no

Manual Colors

yes

Milestones

(based on Jira issues)

yes

Milestones

(based on basic tasks)

no

Estimates

  • Original estimate yes

  • Story points no

  • Remaining estimate no

  • Time spent no

Status

no

The initial status of a project workflow is applied to all copied tasks.

Version, Component, Sprint.

no

During cloning, only Jira issues are created. BigPicture does not make any other changes in the target Jira project. No other items, such as versions, components, or sprints, are created.

Scheduling mode

no

The scheduling mode of duplicated tasks is set based configuration of the target box.

Clone failure - required fields

For a Jira issue to be created, all required fields must be filled in. The required fields are based on Jira settings and can vary from project to project.

During cloning, BigPicture copies a limited number of fields. If any required fields in the target project aren’t filled in during cloning, issues can’t be created.

Solution 1: make fields optional (adjust Jira settings)

Solution 2: import issues instead of cloning the scope

Export and import using Jira

You can use Jira to duplicate tasks:

  1. Export the issues using Jira

  2. Import data to the new target project

Import from a file

Requires BigTemplate app.

Use BigPicture to import data from:

  • mpp

  • mpx

  • csv

  • xlsx

  • xlsx

  • ods

  1. Prepare the export file

  2. Set up a Jira project to which the tasks will be added to
    Create a new Jira project. Make sure to use the 'create with shared configuration option' to make sure the new project is capable of storing the same data that is present in the exported CSV file.

  3. Add the new project to box scope

  4. Run import