Manual task structure
About manual task structure
You can structure your tasks manually or use the structure builders. You can use both ways and generate a complex structure but let's start with the basics.
Before you start structuring your tasks, make sure that you understand the basic concepts related to task scheduling (see the Automation (auto-scheduling) page).
Structure tasks manually
The Gantt and Scope modules allow you to structure your tasks manually. There are different ways to do that, including:
Drag and drop
Keyboard shortcuts
Arrows on the Scope module's header
Arrows on the task vertical dialog
You can move selected tasks or groups of tasks (using the multi-select feature).
Once the parent-child relationship is created, it will appear in all modules that can display the task structure: Board backlog, Scope, Gantt, and WBS widget.
Indent and outdent tasks
Use the arrows in the dialog, which appears when you click on a task, to structure your tasks manually:
An arrow pointing right will indent the task or SHIFT + ->
An arrow pointing left will outdent the task or SHIFT + <-
See the example from the Gantt module.
See the example from the Scope module.
Active structure builder conflicts
When a structure builder is enabled, BigPicture will block an operation if it leads to a conflict, and you will see a warning.
To learn more, see the Task structure page.