Totals
Introduction
Totals will help you plan and monitor the execution of your Timeboxes. You can also use the past data to analyze your teams' performance in-depth.
You have various indicators and aggregations at your disposal. Once you enable them, progress bars will appear in your Timeboxes.
The indicators displayed at the team and unassigned levels include data relevant to a selected team or the unassigned row only. The aggregated data is displayed in each Timebox header.
Enabling the Totals
To enable the features, click on View > Totals > Select the type and aggregation option.
Totals Types and Aggregations
The table below shows different settings and formulas you can apply:
Totals type | Aggregate by | Formula | Screenshot |
---|---|---|---|
Work progress | Story Points (SPs) | Sum SPs of tasks with the "Done" status / Sum SPs of all tasks in Box scope | |
Tasks | Count tasks with the "Done" status / Count all tasks in Box scope | ||
Time spent (TS) | Sum Time Spent of all tasks in Box scope / | ||
Capacity allocation | Original estimate | Sum SPs of all tasks / Box capacity in SPs | |
Remaining estimate (RE) | Sum RE of all tasks / Total Box capacity | ||
Story points | Sum SPs of all tasks / Box capacity in SPs |
Once you enable the duration-based values (Original estimate, Remaining estimate or Time spent) you will be able to choose how the system displays the value in the following formats:
Standard format
Days
Hours
Overallocation warnings
The overallocation warnings can help you and your Team during planning to avoid overcommitting. If allocation exceeds capacity, you will see a warning and the progress bar will indicate overallocation with the color red.