Task dates

Introduction

To start working in BigPicture, you need to create a box and add tasks to this box.

It is not required for tasks to have the start and end dates defined:

  • Tasks have dates if the Start Date and End Date fields are set in Jira and the field mapping is configured. For more information, refer to the Start/end date fields article.

  • Tasks without dates (the Start Date and End Date fields are not set in Jira) can also be added to a box in BigPicture (from the 8.19 version of BigPicture).

Add dates to tasks without dates in BigPicture

There are multiple ways to add dates to tasks without dates. You can add both dates (start date and end date) or only one. A task with one date is semi-transparent, as presented below:

  • No start date:

    Screenshot of a task with no start date.
  • No end date:

    Screenshot of a task with no end date.

Gantt module

To add dates to a task in the Gantt module:

  1. Hover the mouse cursor over a task on the timeline.

  2. Click the + icon.

  3. Edit the Start Date and End Date fields (make sure that these columns are added to the current column view).

Scope module

To add dates to a task in the Scope module:

  1. Find a task.

  2. Edit the Start Date and End Date fields (make sure that these columns are added to the current column view).

Board module

To add dates to a task in the Board module:

  1. Right-click on a task and select Edit.

  2. Complete the dates.

  3. For iterations with precise alignment:

    1. Move a task to such an iteration (dates to a task are added automatically based on dates for an iteration).

Resources module

Unscheduled tasks are visible in the sidebar on the right.

To add dates to a task in the Resources module:

  1. Expand the Unscheduled tasks panel.

  2. Drag tasks onto the grid, or double-click to edit the dates.

Risks module

To add dates to a task in the Risks module:

  1. Right-click on a task and select Edit.

  2. Complete the dates.

     

Delete task dates in BigPicture

You can delete dates from tasks. As a result, such tasks (without dates) disappear from:

Edit task dates in BigPicture

Apart from modifying the Start Date and End Date fields of a task in Jira, you can change dates by the following actions in BigPicture:

  • Edit dates:

    • in the column view

    • in the card view (Board and Risks modules)

  • Move a task:

    • on the Gantt timeline

    • in the Resources module

    • in the Calendar module

  • Inline edit dates:

    • in the Gantt module

    • in the Resources module

Changes in dates caused by other mechanisms

Scheduling

  • Tasks without dates and tasks where dates have been deleted are excluded from the scheduling mechanism (are considered locked tasks). Refer to the Scheduling mode (previously period mode) article.

  • Tasks with one date (start date or end date) are included in the scheduling mechanism.

Auto bottom-up mode

  • A task without dates in the scheduling mode set to auto bottom-up can get dates when dates for children tasks are added.

  • A task with dates in the scheduling mode set to auto bottom-up can lose dates when dates for children tasks are deleted.

Refer to the Scheduling mode (previously period mode) article.

Start date or end date set to estimate

If dates are calculated based on an estimate:

  • Setting a task's start or end date results in calculating the other date automatically.

  • Deleting a task's start or end date results in deleting the other date automatically.

Refer to the One-way sync of Start/End date article.

Auto top-down and Locked modes

  • Tasks in the scheduling mode set to auto top-down or locked can modify the dates of their children.

Task period alignment

  • When the task period alignment of a sub-scope is set to precise alignment, after adding a task to such a sub-box, the dates of a sub-box are assigned to a task automatically.

Refer to the Task period alignment article.

Conversion to milestones

Constraints

Overdue tasks

Critical path

Dependencies

Period warnings

Baselines