How to show total estimation and logged time data per assignee in an Arsenale report

This article explains how to show the sum of total logged time and original estimation data in an Arsenale report.

 Instructions

  1. Navigate to Dataplane Reports > Reports and choose Sum Numeric Field Report

  2. Choose projects or JQL on a need basis and choose the Original Time estimate or Time Remaining or Time spent in Value of Option as per your requirement.

    Sum Numeric Report

     

  3. Add the Assignee field in Segment By Option.

     

  4. Run the report to get total time tracking details per assignee.

 

  • The report could be further customised by adding new fields.