addWorklogAdjustEstimate
Looking for the documentation on the newest versions of SIL Engine and the Simple Issue Language for Jira 8 for Server/Data Center? Click here !
Availability
This routine is available starting with SIL Engine™ 2.5.
This routine is available for Jira server and cloud deployment options.
Syntax
addWorklogAdjustEstimate(issue, user, interval, startDate, comment)
Description
Adds worklog. The remaining time is reduced by the amount of work done, but never below 0.
Parameters
Parameter | Type | Required | Description |
---|---|---|---|
issue | String | Yes | Key of the selected issue. |
user | String | Yes | User name of the selected user. |
interval | Interval | Yes | Interval of time worked. |
startDate | Date | Yes | Start working date. |
comment | String | Yes | Comment that will be posted on the worklog. |
Return type
None
Example
addWorklogAdjustEstimate(key, currentUser(), "2h", currentDate(), "test worklog");
Adds a worklog of 2 hours for the current user on the current issue, recalculating the remaining time automatically.