Estimated and Actual cost fields


When fields are set to "Not Synchronized", the values are stored only in BigPicture.

Estimated cost and Actual cost can each be mapped to a Jira issue field - this means you can associate cost with individual tasks and further automatically aggregate (roll-up) the values in your boxes. 

Cost values need to be manually entered for tasks. 

Use

Cost columns 

To edit the values, edit the column view (Overview/ Gantt/ Scope/ Board modules)

Limitations

Estimated cost and Actual cost are NOT automatically calculated based on the cost rate of the assigned resource ( ONE-33565 - Getting issue details... STATUS ).