Skip to end of banner
Go to start of banner

Copy of Done/Resolved Tickets in last 7 Days

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Next »

Report Purpose: Create a weekly report to that shows all issues that are resolved in the last 7 days.

Instructions

The report is created using Reports and Timesheets for Jira add-on

  1. Go to JiraReports and TimesheetsCustom Report

  2. List type of Report is selected by default

  3. Click on the “+” symbol on the fields in the fields selector on the left to add them to the report

    1. Project: Project Name

      1. Click on the cog icon in the field name to open the Field Settings

      2. Click on Group results by this field checkbox to see results grouped by Project Name

        ART_Done_resolved_ProjectName.jpg

    2. Common: Issue Key and Summary

    3. Common: Priority

    4. Dates: Resolved

      1. Click on the cog icon in the field name to open the Field Settings

      2. In the Filter section, click on the green add rule button “+ Rule” and enter filter as shown in the image below.

        ART_Done_resolved_Time_to_Resolve.jpg

    5. Common: Time to Resolve (Business)

  4. Click on “Run” to see the results

    ART_Done_resolved_Report.jpg

Related articles