Workload vs Capacity Thresholds

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 2 Current »

No task assignment

When a resource is not assigned to any tasks, no workload will be displayed. 

Task assignment exists

Standard

Out of the Box, when the workload is:

  • Less than 75% of the capacity the bar will change  Green color (under-allocation)

  • Between 75% and 100% of the capacity, the bar will change to an Orange color (moderate allocation)

  • Over 100% of the bar will change to Red color (overallocation)

Custom 

BigPicture Enterprise feature → coloring rules can be defined only when using the BigPicture Enterprise add-on.

Levels and colors of the grid in the Resources module depend on Box type settings (Administration> Box type configuration > Resources > Coloring rules) and can't be adjusted for an individual Box. 

  • No labels