Skip to end of banner
Go to start of banner

Workload plans

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 5 Next »

Contents:

Introduction

A workload plan is a calendar used to reflect specific working hours of an individual resource. It is the basis for individual and team capacity calculation. It determines the users' daily, weekly, and monthly capacity, calculated by the Resources and Board modules.

A resource can be assigned to multiple workload plans, for example, a different plan for the summer season and a different one for the winter. 

You can assign workload plans to multiple individuals on the following pages:

  • BigPicture Administration > Resources > Individuals

  • BigPicture Administration > Resources > Workload plans

On the Workload plans page, you can see a list of available workload plans. Information is displayed in three columns:

  • Name

  • Code 

  • Description

image-20240703-072010.png

Security and access

Only a person with the App admin security role or App Resource Admin can access this page. To create workload plans, go to Administration > Resources > Workload plans.

Assign individuals to workload plans

Workload plans can't overlap. You can assign multiple consecutive workload plans to a resource, but they can never overlap. Only one workload plan is applicable at any given moment. 

On the Workload plan page

Method 1

  1. Click the Details button of a workload plan (either by clicking on its name or by clicking the Details button).

    image-20240703-072523.png
  2. Click on the Assigned resources button.

    image-20240703-072755.png
  3. In the pop-up, complete the User, Efficiency, and Start date fields.

  4. When ready, click the plus + button.

    image-20240703-072927.png
  5. Click Assign to confirm.

  6. The resource will appear on the list.

 When you click on the name of a resource, you will be taken to the Administration > Resources > Individuals page of that resource. You can view the details of the workload plan assignment on the resource's timeline.

Method 2 (assign multiple individuals at once)

Assign multiple individuals to a workload plan.

  1. Click Assign individuals on the Administration > Resources > Workload plans page.

    image-20240703-073848.png
  2. Select the workload plan from the list.

  3. Define the Efficiency and Start date fields. The end date will be adjusted automatically.

  4. Select individuals from the list or use the search box to find them faster. The Select all and Deselect All options are useful when assigning multiple individuals.

  5. When ready, click Assign.

    image-20240703-073947.png

On a resource's page (using individuals

Method 1 (manage resource-specific information)

  1. Go to Administration > Resources > Individuals.

  2. Find a resource on the list.

  3. Click on the name of that resource.

  4. Manage workload plans directly on the resource’s page.

Method 2 (assign multiple individuals at once)

  1. Go to Administration > Resources > Individuals.

  2. Click Assign to > Workload plan.

  3. Complete the required fields.

Create workload plans

  1. Click the Add new plan button. 

  2. Provide:

  • Name

  • Code

  • Description (optional field)

A newly created plan is not assigned to any resources. 

To specify Workload plan information, go to a workload plan’s "Details" page.

Details of a workload plan 

To access Workload Plan details, click the name of the plan or the "Details" button:

image2022-1-26_16-57-44.png

The following options are available on a page of each Workload Plan: 

Feature

Description

Section on the Left:

Name

Workload Plan name.

Code

Workload Plan code.

Description

Optional description field.

Max weekly workload

Set a weekly workload limit.

Section on the right:

Save

Save changes.

Delete

Remove a Workload Plan.

Weekly workload total

Displays a sum of distributed weekly hours. 

image2021-5-17_13-28-27.png

Workload distribution

Workload hours are marked in purple on the weekly calendar. The sum of daily working hours results in the weekly workload total.

Assigned resources

View and manage the list of resources assigned to a Workload Plan.

image2021-5-17_13-49-3.png

Max weekly workload 

Specified the weekly workload limit of a Workload Plan.

image2022-1-26_17-4-23.png

Max weekly workload will affect the weekly workload total display color. If the workload distribution of a plan (total of the purple weekly calendar on the right) exceeds the Max weekly workload, the app won't let you save a Workload Plan. For example, the max weekly workload can help App Admin track the maximum legal weekly working hours in a given country. If they have been exceeded, App Admin will not be able to save such a Workload Plan. 

The Max weekly workload doesn't influence the resource capacity - capacity is impacted by the actual purple workload distribution on the right. Resource's capacity is simply a sum of the actual workload distribution in the purple section on the right.

Weekly Workload total 

The app automatically calculates how many hours in total have been distributed over all weekdays.

image2022-1-26_17-8-8.png

The color of the font indicates that:

  • yellow - total distributed workload < Max weekly workload

    image2022-1-26_17-10-14.png

     

  • green - total distributed workload = Max weekly workload

    image2022-1-26_17-12-29.png

  • red - total distributed workload > Max weekly workload

    image2022-1-26_17-14-21.png

Workload Distribution 

Workload hours are marked on the calendar in purple:

image2021-5-17_14-22-21.png

To change the number of daily working hours, modify the number at the top of a given column:

image2021-5-17_14-27-52.png

To move a working hour block, use the drag-and-drop mechanism:

Assigned resources list 

image2022-1-26_17-16-36.png

The pop-up provides the following information:

image2021-5-17_11-42-33.png

Total number of resources assigned to the plan

image2021-5-17_11-40-11.png

List of resources

You can scroll through the list of resources assigned to a given plan:

image2021-5-17_11-41-39.png

The list shows you all resources assigned to a given Workload Plan.

A resource can be assigned to the same workload plan over different periods. 

Keep in mind that a resource can be assigned to multiple workload plans.

 When you click on the name of a resource, you will be taken to the Administration > Resources > Individuals page of that resource. You can view the details of the workload plan assignment on the resource's timeline.

image2022-1-26_17-44-0.png

Remove from the plan

You can remove a user (a particular Workload Plan assignment) directly from the "Assigned Resources" list. 

image2021-5-17_11-53-12.png

The action has to be confirmed:

image2021-5-17_11-53-42.png

If a user was assigned to a Workload Plan only once (there was only one list item for that user), the user is completely removed from the list. 

Add a resource to a plan

You can assign a resource to a workload plan.

Box modules

The daily working hours are the daily capacity of resources used by the Gantt, Resources, and Board modules. For example, Angela is assigned to a plan with 4h working hour day on Thursdays:

Delete workload plans 

You can not delete the default plans.

To delete a plan, click the 'Delete' button

  • on the Workload plans overview page

  • on the Workload plan details page

If a resource is assigned to a deleted plan, the App assigns the Default Workload Plan instead. 

Workload plan overview - delete

Workload plan details - delete

Default workload plan

Default workload plan can't be removed.

When a task is added to the scope of a Box or when the currently assigned plan is deleted, the task assignee is automatically assigned to the default workload plan.

Workload plan efficiency 

(If you want to simulate a non-human resource or use a single user to represent a team, you can use the efficiency multiplier. Alternatively, you can use it to reduce the capacity resulting from the Workload plan by setting a value below 1.)

Non-working days

You can set the work time to 0 to define a non-working day

Maximum work time

The maximum time is 24 hours, and the calendar uses 5 minutes of granulation.

It can exceed the 24-hour limit by specifying 'Efficiency' in the Resource Manager section.

Individual absences

Users can add their own absences using their My settings page. 


  • No labels