Introduction

You can create unlimited Holiday holiday plans to reflect the holidays and observances. Each non-working day resulting form from the holiday plan reduces the capacity (daily capacity to zero) of the assigned resource or the Teamteam. Similarly, like with Workload plans users can be assigned to those plans using the Resource Manager (

You can assign holiday plans to multiple individuals on the following pages:

...

  • BigPicture Administration > Resources > Holiday plans

Info

The App BigPicture can calculate tasks automatically based on the assignee's working days. Jira admins can enable this feature in the BigPicture configuration.

...

The holidays can be grouped into a set, such as European Holidaysholidays. If the organization also has offices in the United States, a holiday set can be created for that region as well. This expedites the planning process as information is easily accessed across the organisationorganization.

Security and access

Only a person with the App Admin or App Resource Admin security role can access this page.

To access this page, go to Administration > Resources > Holiday plans.

Holiday modes

The table below shows the difference between available modes:

Holiday mode

Description

Non-working days

The non-working days of the week are marked with a grey

 colour

 color circle.

Fixed mode

Dates are automatically moved to the next year and are marked with a red

 colour

 color circle.

Floating

Dates are not moved to the next year automatically and are marked with blue

 colour

 color circle.

Extra working days

The extra days are marked with a white

colour

color circle.

You can view all the holidays and inline edit the holiday name field:Image Removed

...

Default

...

holiday plan

When a task is added to the scope of a Box, or when the currently assigned plan is deleted, the task assignee is automatically assigned to the default holiday plan.

...

Add new holiday plans

Click the 'Add new plan' button and enter the name and code (max. 10 characters). The name of the currently active plan is displayed in the resource list on the Resource manager page.

Image Removed

Editing the calendar

Click the name of the plan or the 'Details' button to Administration > Resources > Individuals page.

...

Assign individuals to holiday plans

Assign multiple individuals to a holiday plan.

  1. Click Assign individuals on the Administration > Resources > Holiday plans page.

  2. Select the holiday plan from the list.

  3. Define the start date. The end date will be adjusted automatically based on the start date of the previous plan.

  4. Select individuals from the list or use the search box to find them faster. The Select all and Deselect All options are useful when assigning multiple individuals.

  5. When ready, click Assign.

...

Edit the calendar

Click the plan's name or the Details button to view and edit the holiday dates. If you want to change the name or the code, click the 'Edit ' button.

When in the detail view, click the 'Click the Edit details ' button to change holidays in the detail view. Click the dates which that you want to convert to holidays and select the Holiday holiday mode:Image Removed

...

Use the arrows in the top right corner to move the calendar to the next year:Image Removed

...

For example, Angela is assigned to a Holiday plan with holidays on the 3rd and 4th of August:Image Removed

...

On these dates, the daily capacity is reduced to zero in the Resources module and the scheduling mechanism moves the tasks to start on a the first working dayImage Removed

...

.

...

Delete holiday plans

To delete a plan, click the 'Delete' on the details page or on the Holiday plans page. You can not can’t delete the default plans.

Info

If a resource was assigned to a deleted plan, the App BigPicture assigns the Default Holiday Plan default holiday plan instead. 

...

Default

...

holiday plan

Each tasks assignees task assignee is automatically assigned to the default holiday plan once a tasks task is added to the Boxbox's scope, or when the currently assigned plan is deleted. Image Removed

...

Individual

...

absences

Users can can add their own absences using  using their "My settings"page. 

Security and access

...