Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Table of Contents

You can track project milestones using the Infobar section in the Gantt module. Navigate to the selected milestone by clicking on the "Target" icon next to the milestone on the list.

Convert tasks to milestones

Milestones can be interpreted as:

  • Markers of reaching an identifiable stage in any task or project.

  • Software release life cycle states.

On the timeline, milestones are represented as diamonds.

Milestones represent a point in time - milestone duration is 0 days.

Info

Parent tasks cannot be converter to milestones. 

If a task has children in the task tree (WBS) it can't be converted into a milestone - scheduling mode interactions between parent/child would not be possible. 

Image Removed

Convert a single task to a milestone

Excerpt

To convert a single task to a milestone or vice versa, right-click on the selected task (on the task list) or use the ". . ." button in the vertical dialog.

Info

You can also use inline editing to turn a task into a milestone. 

...

Image Added

Start/end date recalculation

During conversion, the task end date is set as the milestone date.

Before conversion:
Image Modified

After conversion:
Image Modified

Convert multiple to milestones / tasks

Use the multi-select option to select a few tasks and milestones and right-click to "Convert all to...":

  • Milestone

  • Task

When you select a milestone and a task and right-click "Convert all to.. > Task":

  • A milestone is converted to a task.

  • A task remains unchanged because it is already a task.

...

Image Added

Convert a task with one date to a milestone

Excerpt
nameconvert-task-one-date

When a task with one date (“Start Date” or “End Date”) is converted to a milestone, the “Start Date” becomes the same as the “End Date”.

...

Image Added

Create a basic task as a milestone

  1. Click the (plus icon)

...

  1. Create task Basic task.
    Image Modified

  2. Fill in the task information.
    Image Modified

  3. Activate the toggle switch.

...

  1. Image Added

Milestone synchronization

You can synchronize milestone information using the "Label" field. When you convert a task to a milestone, the app will create a #milestone label:

...

Labels will be added or removed in the following scenarios:

  • A task is converted into a milestone -> the #milestone label in Jira is added.

  • A milestone is converted into a regular task -> the #milestone label in Jira is removed.

  • A milestone is converted into a parent task -> the #milestone label in Jira is removed.

...

Note: Depends on field mapping.

Milestone overview - Infobar

You can show the list of milestones using the Gantt's Infobar:

  • Only milestones expanded on the Gantt chart are visible on the list.

...

...

    ...

    • If a user wants to see only milestones from selected parent tasks, they need to expand those parent tasks and collapse parent tasks they are not interested in.

    • If a user wants to see all the milestones in the program, they need to expand all of the tasks by clicking "Expand all" on a tree root column header.

    ...

    • Image Added

    Dependencies vs Milestones

    Dependencies are adjusted to account for

    ...

    the fact that a Milestone is a point in time (has a single date). Milestones don't artificially make the path between linked tasks longer. 

    ...

    The calculation is affected when:

    ...

    • A milestone is a target of a dependency

    ...

    • Start to end OR end to start

    Dependencies to Milestones 

    When a Milestone is a target of a dependency:

    Task to Milestone OR

    Milestone to Milestone

    non-ASAP

    ASAP

    End → start

    Milestone date >= task end date

    Milestone date = task end date

    End → end

    regular dependency behavior

    regular dependency behavior

    Start → end

    Milestone date <= Task Start Date 

    Milestone date = task start date 

    Start → start

    regular dependency behavior

    regular dependency behavior

    "End to start" dependencies are adjusted to account for

    ...

    the fact that a Milestone is a point in time (has a single date).

    When Milestone is a target:

    • ASAP - the Milestone date has to be the same as the source end date

    • non-ASAP - the Milestone date has to be the same or later

    ...

    • than the source end date

    ...

    Image Removed

    "Start to end" dependencies are adjusted to account for

    ...

    the fact that a Milestone is a point in time (has a single date).

    When Milestone is a target:

    • ASAP - the Milestone date has to be the same as the source start date

    • non-ASAP - the Milestone date has to be the same or later

    ...

    • than the source start date

    Image Removed

    ...

    "End to end" dependencies behave normally.

    ...

    "Start to start" dependencies behave normally.

    ...


    Dependencies from Milestone to task 

    Dependencies from Milestones to tasks behave normally (same as task → task dependencies).

    ...

    Table of contents

    ...