You can track project milestones using the Infobar section in the Gantt module. Navigate to the selected milestone by clicking on the "Target" icon next to the milestone on the list.
Convert tasks to milestones
Milestones can be interpreted as:
- Markers of reaching an identifiable stage in any task or project.
- Software release life cycle states.
On the timeline, milestones are represented as diamonds.
Milestones represent a point in time - milestone duration is 0 days.
Convert a single task to a milestone
To convert a single task to a milestone or vice versa, right-click on the selected task (on the task list) or use the ". . ." button in the vertical dialog.
Start/end date recalculation
During conversion, the task end date is set as the milestone date.
Before conversion:
After conversion:
Convert multiple to milestones / tasks
Use the multi-select option to select a few tasks and milestones and right-click to "Convert all to...":
When you select a milestone and a task and right-click "Convert all to.. > Task":
- A milestone is converted to a task.
- A task remains unchanged because it is already a task.
When a task with one date (“Start Date” or “End Date”) is converted to a milestone, the “Start Date” becomes the same as the “End Date”.
Create a basic task as a milestone
- Click the + (plus icon) > Create task > Basic task.
- Fill in the task information.
- Activate the toggle switch.
Milestone synchronization
You can synchronize milestone information using the "Label" field. When you convert a task to a milestone, the app will create a #milestone label:
Labels will be added or removed in the following scenarios:
- A task is converted into a milestone -> the #milestone label in Jira is added.
- A milestone is converted into a regular task -> the #milestone label in Jira is removed.
- A milestone is converted into a parent task -> the #milestone label in Jira is removed.
To generate labels you need to configure the filed mapping in Task when a milestone is created.
Milestone overview - Infobar
You can show the list of milestones using the Gantt's Infobar:
Dependencies vs Milestones
Dependencies are adjusted to account for a fact that a Milestone is a point in time (has a single date). Milestones don't artificially make the path between linked tasks longer.
Calculation is affected when:
- a Milestone is a target of a dependency
- start to end OR end to start
Dependencies to Milestones
When a Milestone is a target of a dependency:
Task to Milestone OR Milestone to Milestone | non-ASAP | ASAP |
---|
End → start | Milestone date >= task end date | Milestone date = task end date |
End → end | regular dependency behavior | regular dependency behavior |
Start → end | Milestone date <= Task Start Date | Milestone date = task start date |
Start → start | regular dependency behavior | regular dependency behavior |
"End to start" dependencies are adjusted to account for a fact that a Milestone is a point in time (has a single date).
When Milestone is a target:
- ASAP - the Milestone date has to be the same as the source end date
- non-ASAP - the Milestone date has to be the same or later then the source end date
"Start to end" dependencies are adjusted to account for a fact that a Milestone is a point in time (has a single date).
When Milestone is a target:
- ASAP - the Milestone date has to be the same as the source start date
- non-ASAP - the Milestone date has to be the same or later then the source start date
"End to end" dependencies behave normally.
"Start to start" dependencies behave normally.
Dependencies from Milestone to task
Dependencies from Milestones to tasks behave normally (same as task → task dependencies).