A Workload Plan is a calendar used to reflect specific working hours of an individual resource. It is the basis for individual and team capacity calculation.

It determines the users' daily, weekly and monthly capacity which is calculated by the Resources and Board modules.

Similarly, like with Holidays plans users can be assigned to those plans using the  Resource Manager. A Resource can be assigned to multiple workload plans, for example, a different plan for the summer season and a different one for the winter one. 

On the "Workload plans" page you can see a list of available workload plans. 

Image Modified

Information is displayed in three columns:

  • Name
  • Code 
  • Description

Image Modified


Anchor
AssigningWorkloadPlans
AssigningWorkloadPlans

Assigning Workload Plans

Info

Workload Plans can't overlap. You can assign multiple consecutive Workload plans to a resource, but they can never overlap. Only one workload plan is applicable at any given moment. 

You can assign Workload Plans to resources:

On a Workload Plan page 

Open "Details" of a Workload Plan (either by clicking on its name or by clicking the "Details" button):
Image Modified
Next, click on the "Assigned Resources" button at top with:
Image Modified
In the pop-up, select:

  • a User
  • Efficiency
  • Start date

Image Modified

Click the "+" button to add a resource to the Workload Plan:
Image Modified

Confirm the change:
Image Modified

The resource will appear on the list:
Image Modified

Tip

 When you click on the name of a Resource, you will be taken to the "resource manager" page of that resource. You can view the details of the Workload Plan assignment on the resource's timeline.

On a resource's page (using individuals

To manage resource-specific information go to Administration > Resources > Individuals and open a resource page by clicking on the name of a given resource.

You can manage Workload Plans directly on the resource's page.

Image Modified


Creating Workload Plans

Click the "Add new plan" button and enter the name and code (max. 10 characters). 

Provide:

  • Name
  • Code
  • Description (optional field)

Image Modified

A newly created plan is not assigned to any resources. 

To specify Workload plan information, go to the "Details" page of a workload plan.

...

...

Details of a Workload Plan 

Image Modified

To access Workload Plan details, click the name of the plan or the "Details" button:
Image Modified

The following options are available on a page of each Workload Plan: 

FeatureDescription
Section on the Left:

Image Modified

NameWorkload Plan name.
CodeWorkload Plan code.
DescriptionOptional description field.
Max weekly workloadSet a weekly workload limit.
Section on the right:

Image Modified

SaveSave changes.
DeleteRemove a Workload Plan.
Weekly workload total

Displays a sum of distributed weekly hours. 
Image Modified

Workload distributionWorkload hours are marked in purple on the weekly calendar. The sum of daily working hours results in the weekly workload total.
Assigned resources

View and manage the list of resources assigned to a Workload Plan. 
Image Modified

...


Max weekly workload 

Specified the weekly workload limit of a Workload Plan. 
Image Modified

Info

Max weekly workload will affect the weekly workload total display color. If the workload distribution of a plan (total of the purple weekly calendar on the right) exceeds the Max weekly workload, the app won't let you save a Workload Plan. For example, the max weekly workload can help App Admin track the maximum legal weekly working hours in a given country. In the case they have been exceeded, App Admin will not be able to save such Workload Plan. 

The Max weekly workload doesn't influence the resource capacity - capacity is impacted by the actual purple workload distribution on the right. Resource's capacity is simply a sum of the actual workload distribution in the purple section on the right

...

.

...


Weekly Workload total 

The app automatically calculates how many hours in total have been distributed over all weekdays. 
Image Modified

The color of the font indicates that:

  • yellow - total distributed workload < Max weekly workload
    Image Modified 
  • green - total distributed workload = Max weekly workload
    Image Modified
  • red - total distributed workload > Max weekly workload
    Image Modified

Workload Distribution 
Anchor
WorkloadDistribution
WorkloadDistribution

Workload hours are marked on the calendar in purple:
Image Modified

To change the number of daily working hours modify the number at the top of a given column:
Image Modified

To move a working hour block use the drag-and-drop mechanism:

Multimedia
nameDrag-and-drop.mov
width100%
height100%

Assigned resources list 
Anchor
AssignedResources8.1
AssignedResources8.1

Image Modified

The pop-up provides the following information:
Image Modified

Total number of resources assigned to the plan

Image Modified

List of resources

You can scroll through the list of resources assigned to a given plan:
Image Modified

Info

The list shows you all resources assigned to a given Workload Plan.

A resource can be assigned to the same workload plan over different time periods. 

Image Modified


Tip

Keep in mind, a resource can be assigned to multiple Workload Plans.

When you click on the resource name, you will be taken to the "Resource manager" page of a given user, where you can view all their assignments in detail. 

Expand

Image Modified



Remove from the plan

You can remove a user (a particular Workload Plan assignment) directly from the "Assigned Resources" list. 
Image Modified

The action has to be confirmed:
Image Modified

If a user was assigned to a Workload Plan only once (there was only one list item for that user), the user is completely removed from the list. 

Add a resource to a plan

You can assign a resource to a workload plan.

Box modules

The daily working hours are the daily capacity of resources used by the Gantt, Resources and Board modules. For example, Angela is assigned to a plan with 4h working hour day on Thursdays:

Image Modified

Anchor
DeletingWorkloadPlans8.1
DeletingWorkloadPlans8.1

Deleting Workload Plans 

You can not delete the default plans.

Info

To delete a plan click the 'Delete' button

  • on the Workload plans overview page
  • on the Workload plan details page

If a resource was assigned to a deleted plan, the App assigns the Default Workload Plan instead. 

Workload Plan Overview - delete

Image Modified

Workload Plan Details - delete

Image Modified

Default Workload plan

Info

Default Workload Plan can't be removed.

When a task is added to the scope of a Box, or when the currently assigned plan is deleted, the task assignee is automatically assigned to the default workload plan.

Image Modified


Workload Plan Efficiency 
Anchor
WorkloadPlanEfficiency
WorkloadPlanEfficiency

Info

(If you want to simulate a non-human resource or use a single user to represent a team, you can use the efficiency multiplier. Alternatively, you can use it to reduce the capacity resulting from the Workload plan by setting a value below 1.)


Non-working days

You can set the work time to 0 to define a non-working day

Maximum work time

The maximum time is 24h and the calendar uses 5 minutes of granulation.

Info

It is possible to exceed the 24h limit by specifying the 'Efficiency' in the Resource manager section.

Individual Absences

Users can add their own absences using their "My settings" page. 


Security and access

  • Only a person with the App admin security role or App Resource Admin can access this page.
  • To create workload plans go to Administration > Resources > Workload plans