Automation (auto-scheduling)

Introduction

BigPicture provides several automation mechanisms that help you save time and keep hundreds of tasks under control and within deadlines.

You can find a list of solutions below.

Constraints

Task in multiple boxes

If you make changes to a task in multiple boxes, the changes are automatically implemented in other boxes. When each box is configured differently, the resulting task's period is 'evenly shaped' by the rules of each box. The task's position and duration on the timeline remain the same in all boxes.

Automation vs. tasks with the Done status

Tasks with the Done status are excluded from any scheduling automation rules. Such tasks aren’t affected by dependencies, scheduling mode of other tasks (parent and children).

Only manual changes to the dates and/or duration affect those tasks.

Structure builders and field sync

BigPicture automatically updates fields in Jira (or another platform) once you edit a task or create a dependency. Changes to tasks can be made also by automation based on modifications to the task position in the task structure.

If you move a task to an appropriate place in the task structure, BigPicture can automatically perform the following actions:

  • Assign a task to the correct sprint, version, or epic.

  • Unlink a task from the correct sprint, version, or epic.

  • Create links between tasks in Jira.

  • Delete links between tasks in Jira.

Find out more on this page.

Scheduling rules - priorities

According to multiple rules, the auto-scheduling function aims to calculate the task's period (start and end dates). Those rules are applied simultaneously, but each has its priority. Depending on the implemented rules, you can end up with different setups of scheduling functions for each task.

The table below lists the rules according to the following priority:

Priority

Applicable rule

Priority

Applicable rule

1.

Scheduling mode applied to a task

2.

Parent-child relation

3.

Calendar (non-working days)

4.

Dependencies

Examples

Examples

  • When a task is in manual scheduling mode, start/end dates are unaffected by dependencies and the calendar.

  • When a task is in auto top-down scheduling mode, start/end dates are unaffected by dependencies if dependencies were to move children of such a task outside the date range of the parent task.

Dependencies

Dependencies are relationships between tasks, milestones, and other items. The mechanism can simultaneously move one or more tasks linked to a moving task. By defining dependencies, task dates and other initiatives are updated automatically due to changes made to a project.

You can also define dependencies between initiatives such as versions or projects.

If you do NOT want dependencies to affect tasks, you can turn off automation by setting an appropriate scheduling mode.

Find out more on this page.

Scheduling mode

The scheduling mode is a task parameter in BigPicture that determines what automation mechanisms impact task dates. There are four scheduling modes explained further below:

  • Auto basic

  • Auto bottom-up

  • Auto top-down

  • Manual

  • Locked

Scheduling mode

Description

Scheduling mode

Description

Auto basic

 

Auto basic mode is the default scheduling mode in BigPicture.

Tasks in Auto basic mode react to automation based on non-working days, dependencies, and parents in Auto top-down and Locked mode.

Tasks set to Auto basic mode do NOT affect children’s dates (as tasks in Auto bottom-up mode) and do NOT shift children’s tasks when tasks are moved.

 

Auto bottom-up

Parent task dates are adjusted to match the period of their children’s tasks.

Use case: You want the end date of the epic to be defined by the latest task that belongs to the epic.

Auto top-down

A parent task repositions its children tasks to fit within a parent task period.

Use case: You want tasks to be moved back in time so that they do not exceed the end date of a version or project.

Manual

Automation mechanisms such as dependencies, calendars, and parent-child relations do NOT work on such tasks.

Use case: You want a task to be completed on the weekend or unaffected by any automation mechanism (task dates have to be manually changed).

Locked 

The mode blocks the possibility of changing the duration and position of tasks by automation and other users.

Children tasks dates do NOT exceed the end date of a parent task (as in the auto top-down mode).

Use case: You want a task to be necessarily scheduled on specified dates.

To change the start/end dates of a locked task, you have to change the scheduling mode first.

 

Find out more on this page.

Calendar (non-working days)

You can mark days in the calendar as non-working days by setting schedules or assigning a day off to an employee. BigPicture recognizes non-working days and adjusts a task period accordingly. If you plan a task or part of your task's period on a non-working day, it will be moved or extended, or shortened.

Find out more on this page.

If you do NOT want non-working days to affect the duration of tasks, you can turn off automation by setting an appropriate scheduling mode.

Calculate task dates based on estimates or logged time

Another solution that helps you manage and monitor tasks more efficiently is the possibility to automatically calculate task dates based on estimates or the time logged on tasks.

Activating the mechanism modifies the way of editing the “Start Date” field. Entering a new “Start Date” moves a task. The duration of a task is NOT changed, and its “Original Estimate” remains unchanged.

Automatic calculation of task dates based on estimates proves helpful when:

  • The “Original Estimate” field contains estimates for a task. If you enter the “Start Date”, the “End Date” is calculated automatically based on an estimate.

  • You monitor the project estimate based on the sum of the “Original Estimate” for all tasks in that project. If you update task dates, task estimates, along with the final project estimate, are updated automatically.

  • You want task dates adjusted to the time logged on a task. As a result, you can track in real-time how tasks match the dates to the actual progress of work logged by other employees.

Find out more on this page.

Align task dates with iteration dates

BigPicture offers the possibility to align task dates with iteration dates automatically. With such a solution, you can see a visualization of tasks in the Gantt module, or it is possible to automatically set expected end dates for tasks (e.g., bug type) that are assigned to a given sprint.

Find out more on this page.

Changing absences for assignee

Task is re-scheduled when absence is added or removed from the assignee. For more details, check the Auto recalculation based on the assignee option.