Burndown chart shows you how your team is progressing against the work for a release or an issue. You will be able to see if your release or issue is on track, ahead, or behind.
๐ Read more about Release burndown charts in our blog article
How to access Burndown chart
Go to Swanly viaย Appsย >ย Swanly roadmaps
Click on release or issue name to open the report view
Click Expand button in the top right corner of the screen
Click on the Burndown chart tab
To display the Burndown chart you will need to have the following:
set start and end date for your release (issue)
add issues in version (child issues)
The vertical % In Progress axes chart shows you a percentage of remaining work and gives you 3 options to track progress:
Issue count
Story points
Original time estimate
On horizontal Time axes, it shows dates, and Release (Issue) end date is highlighted.