Start/End date fields
These fields determine the start and end positions of the task on the timeline.
Overwrite Jira task data with data from the App
If you want to use a different field, it is possible to overwrite Jira task data with data from BigPicture. When you select a field other than currently used, you can switch on the "Overwrite Jira task data with data from the App" option below.
This action is irreversible.
In general, there are three main strategies for task synchronization:
Not synchronized - use this option if you do not want to update Jira issues while still being able to plan using the Gantt module. Changes to date estimates will not sync to Jira, meaning task start and end dates might differ from those in Jira issues.
Two 'Date picker' (or 'Date time picker') fields - recommended when assignees work on multiple tasks simultaneously.
One 'Date picker' (or 'Date time picker') field and a time estimate field (Original estimate or Time spent + Remaining estimate) - recommended for working on one task at a time.
The App will not update fields mapped above as a start and end date if they are not defined in the Jira Project Screen scheme (excluding Time Spent + Remaining Estimate). In other words, for synchronization to work, you must ensure that the fields exist in Jira for a particular project.
If you need more details, take a look at the example:
Scheduling impact
From the 8.15 version of BigPicture onwards.
Start/end dates mapped to estimate fields
Start date
can be mapped to the Original Estimate
End date
can be mapped to Original Estimate or
Time Spent + Remaining Estimate
Note: Only one of the fields (either start or end date) can be mapped to an estimate. The other field must remain as a date field, such as the start/end date.
Expected behavior (dates exist)
You can update the following values:
star/end date
task duration
the estimate field
Updates can be done by:
change of a field value, for example, by editing a value in a column in BigPicture
adjustment of a task position and length on a Gantt chart
New start/end value (inline editing or update of a field on Jira issue page)
Behavior is the same regardless of mapping:
Change of the start date results in a task being moved.
Change of the end date results in a task being resized. The estimate field and task duration field reflect the change. The start date is unaffected.
Change | Result | value | Affected | Mapping |
---|---|---|---|---|
start date updated | Task moved | start date |
| |
end date | ||||
task duration |
| |||
Estimate |
| |||
end date updated | Task resized | start date |
| |
end date | ||||
task duration | ||||
Estimate |
New task duration OR estimate field value
Behavior depends on the mapping:
the date mapped to the estimate is adjusted
Change | Result | value | Affected | Mapping |
---|---|---|---|---|
task duration updated OR estimate value updated | Task resized | start date |
| |
end date |
| |||
task duration | ||||
estimate | ||||
start date |
|
| ||
end date | ||||
task duration | ||||
estimate |
Task position adjusted on the timeline
All fields are updated to reflect the task position on the timeline.
The position of the “Overwrite Jira task data with data from the App” slider is ignored. BigPicture operates based on the built-in field values.
Affected by
The "Respect Jira screen scheme" toggle switch applies to start/end date field mapping.