Unscheduled tasks are:
tasks without start and end dates defined
tasks with one date (start or end date defined)
For better management, such tasks are easily available from the “Unscheduled tasks” sidebar in the Resources module.
The “Unscheduled tasks” sidebar is available from the 8.19 version of BigPicture.
To see unscheduled tasks, open the sidebar on the right.
The following columns are available in the “Unscheduled tasks” sidebar:
Key
Summary
Start Date
End Date
Assignee
Original Estimate
You can find tasks quickly with the search box functionality. The search box operates in two modes:
Text search
JQL search
You can quickly make changes (e.g., add dates, change an assignee, modify a summary) with inline editing.
To schedule tasks, you can:
Method 1:
Drag a task onto the grid.
Make changes if necessary.
To confirm, click “Schedule”.
Dates cannot be added to parent tasks set to Auto bottom-up scheduling mode. Warning appears as parent’s dates depend on the dates of its subtasks.
Method 2:
Double-click and complete the missing dates.