Creating dependencies

You can create a dependency in the following ways:

  1. Click on the dot next to the taskbar and drag and drop it on the target task, or drop it to the dependency dot of the target task. When you hover over a dependency dot or a taskbar of the target task, both the dot and half of a taskbar pulsate. 

  2. Click the dot next to the taskbar when you hover over the task with the mouse.

  3. Create dependencies directly on a Jira issue page.

Example 1

  1. Click on the dot next to a taskbar.

  2. Drag and drop it on the target task, or drop it to the dependency dot of the target task.

The video presents creating a dependency by dragging and dropping.

2024-05-21_12-24-57.mp4

Example 2

  1. Create the task dependency by clicking the dot.

  2. The source task field is automatically filled in. 

  3. Find a target task.

  4. Choose a dependency type (hover over a camera icon to see an explanation of each dependency type).

  5. Define a lag time.

  6. If needed, enable the ASAP mode.

  7. When ready, click Save.

The video presents creating a dependency by clicking the dot.

2024-05-21_12-29-06.mp4

Example 3

Create a dependency directly in Jira.

ASAP mode hotkey

As you create a dependency by manually dragging and positioning the arrow, as you hover the mouse over the target task, you see a message letting you know that you can change the ASAP on/off by holding the ALT key