Introduction

To start working in BigPicture, you need to create a box and add tasks to this box.

It is not required for tasks to have the start and end dates defined:

  • Tasks have dates if the “Start Date” and “End Date” fields are set in Jira and the field mapping is configured. For more information, refer to the field mapping article.

  • Tasks without dates (the “Start Date” and “End Date” fields are not set in Jira) can be also added to a box in BigPicture (from the 8.19 version of BigPicture).

Add dates to tasks without dates in BigPicture

There are multiple ways to add dates to tasks without dates. You can add both dates (“Start Date” and “End Date”) or only one of them. A task with one date is semi-transparent as presented below:

  • No “Start Date”:

...

  • Image Added
  • No “End Date”:

...

  • Image Added

Gantt module

  • Hover the mouse cursor over a task on the Gantt timeline and click the “+” icon to add dates to a task.

...

  • Image Added
  • Edit the “Start Date” and “End Date” fields in the column view (make sure that these columns are added to the current column view).

...

  • Image Added

Scope module

  • Edit the “Start Date” and “End Date” fields in the column view (make sure that these columns are added to the current column view).

...

  • Image Added

Board module

  • Right-click “Edit” to add dates to a task in the card view.

...

  • Image Added
  • For iterations with precise alignment, move a task to such an iteration (dates to a task are added automatically based on dates for an iteration).

Resources module

  • Unscheduled tasks are visible in the sidebar on the right. Drag tasks onto the grid or double-click to edit the dates.

...

  • Image Added

Risks module

  • Right-click “Edit” to add dates to a task in the card view.

...

  • Image Added

Delete dates from tasks in BigPicture

You can delete dates from tasks. As a result, such tasks (without dates) disappear from the Gantt timeline, the Resources module, and the Calendar module.

Edit dates of tasks in BigPicture

Apart from modifying the “Start Date” and “End Date” fields of a task in Jira, you can change dates by the following actions in BigPicture:

  • Edit dates:

    • in the column view

    • in the card view (Board and Risks modules)

  • Move a task:

    • on the Gantt timeline

    • in the Resources module

    • in the Calendar module

  • Inline edit dates:

    • in the Gantt module

    • in the Resources module

Changes in dates caused by other mechanisms

Scheduling

  • Tasks without dates and tasks where dates have been deleted are excluded from the scheduling mechanism (are considered locked tasks).

  • Tasks with one date (“Start Date” or “End Date”) are included in the scheduling mechanism.

Auto bottom-up mode

  • A task without dates in the scheduling mode set to auto bottom-up can get dates when dates for children tasks are added.

  • A task with dates in the scheduling mode set to auto bottom-up can lose dates when dates for children tasks are deleted.

“Start Date” or “End Date” set to estimate

If dates are calculated based on an estimate:

  • Setting the “Start Date” or “End Date” to a task results in calculating the other date automatically.

  • Deleting the “Start Date” or “End Date” of a task results in deleting the other date automatically.

Auto top-down and Locked modes

  • Tasks in the scheduling mode set to auto top-down or locked can modify the dates of their children.

Task period alignment

  • When the task period alignment of a sub-scope is set to precise alignment, after adding a task to such a sub-box, the dates of a sub-box are assigned to a task automatically.

Conversion to milestones

Expand
titleExpand to see more
Insert excerpt
Milestones
Milestones
nameconvert-task-one-date

Constraints

Overdue tasks

Expand
titleExpand to see more
Insert excerpt
Overdue tasks
Overdue tasks
nameoverdue-tasks

Critical path

Expand
titleExpand to see more
Insert excerpt
Critical path
Critical path
namecritical-path

Dependencies

Expand
titleExpand to see more
Insert excerpt
Displaying Dependencies
Displaying Dependencies
namedependencies-task-dates

Period warnings

Expand
titleExpand to see more
Insert excerpt
Period warnings
Period warnings
nameperiod-warnings-dates

Baselines

Expand
titleExpand to see more
Insert excerpt
Baselines
Baselines
namebaselines-task-dates

...