In this view, you can assign your resources to predefined Skills, Workload Plans, and Holiday Plans or plan Absences in this view.

Security and

...

Access

  • Only a person with the App Admin and App Resource Admin security role can access this page.

  • To assign resources, go to Administration > Resources > Individuals > click the resource name.

...

Current assignment

In Resource manager, at the top of a page of a given resource, you can see their current Absences, Holiday Plans, Workload Plans, and Skills:Image Removed

...

The timeline on the right helps you visualize Absences, Holiday Plans, and Workload Plans:Image Removed

...

Additionally, current items can be highlighted (yellow) if the Highlight present data option on a timeline is selected.Image Removed

...

Timeline navigation

Feature

Description

Scroll

When

Hold Shift and scroll using the mouse wheel when you hover your mouse over the timeline

, hold Shift and scroll using the mouse wheel


OR

Image Removed
image2021-5-13_14-47-44.pngImage Added

You can scroll

10

ten years in each direction.

Image Removed
Image Added

The "Today" button centers the view on the present date. 

Image Removed
image2021-5-13_14-49-13.pngImage Added
Image Removed
Image Added

Zoom out.

Image Removed
Image Added

Zoom in. 

Image Removed
Image Added

Display options pop-up menu: allows you to show/hide week numbers on the timeline.

Image Removed
Image RemovedImage Removed
image2021-5-13_14-55-32.pngImage Addedimage2021-5-13_14-56-24.pngImage Added
Image Added

Applicable to the entire page (including sections below the timeline). 

View options allow you to hide/display items based on their relation to the present day. 

Image Removed
Image Added

Highlight present data - when selected, items currently relevant are highlighted in yellow.

Image Removed
image2021-11-2_9-30-22.pngImage Added

Teams

Total The total team assignment of a resource (across all Boxes) can be reviewed on the resource details page. Image Removed

...

Team assignment (availability, period, etc.) has to be edited in a Box where it has been added. This information is in the created in column. Listed items work as links that take you to the Box in question.Image Removed

...

Related to to the column contains info about what sub-Boxes are affected by team assignment → click on the number to see a pop-up containing the list of Boxes that inherited the assignment. The ID column works as a link to a given Box.Image Removed

...

Skills

...

In order to To assign a resource to a skill, the App admin need needs to define the skills first in the App's administration. Each skill has a start date (required field) and end date. Resources can be assigned to multiple skills at the same time.

The order of the listed Skills is sorted by the end date, then by the start date (oldest "end date" skills at the bottom, newest at the top. If the end date is the same, oldest "start date" at the bottom, newest latest start date at the top).Image Removed

...

Once assigned, the new skill will be visible in the Resources module when the Skill panel is enabled.

Assigning Skills

To assign a skill, click on the "+" icon:Image Removed

...

In the pop-up box, select a skill name and the Name field and choose a skill from the drop-down list (the skills on the list are sorted alphabetically). Select the timeframe for the skill assignment:Image Removed

...

Click the "Add" button. The skill will be visible on the list. Image Removed

...

Editing Skills

Click on the Image Modifiedicon to edit a skill entry:Image Removed 

...

A details pop-up will appear. After making adjustments, hit "Save". Image Removed

...

Removing Skills

Click on the Image Modified icon to remove a skill:Image Removed

...

Confirm the operation:Image Removed

...

Anchor
assigningworkloadplans
assigningworkloadplans

...

Resources can be assigned to multiple workload plans but not at the same timesimultaneously. The App admin can define the workload plans in the App's administration. When assigning posting a resource to a workload plan, both start and end dates are required, and the App will automatically set the end date when a new plan is added. Image Removed

...

Workload Plans are sorted based on their start date (chronological): the newest items are at the top, and the oldest items are on at the bottom (regardless of the order in which items were created). Image Removed

...

Assigning Workload Plans

To assign a Workload Plan, click on the "+" icon:Image Removed
In the pop-up box, select

...

Select a Workload Plan name and the start date in the pop-up box. The end date will be calculated automatically based on the start date of the previous Workload Plan (Workload plans can't overlap).Image Removed 

...

Click the "Add" button. The Workload plan will be visible on the list.Image Removed 

...

Info

The unspecified end date."Image Modified" will automatically change , when you assign a new workload plan. 

Expand

For example, if the "crunch' is supposed to last till the 1st of June, assign the "Default Workload Plan" to start on June 1st. 

The "crunch" end date will automatically be set to the last day of May. 


Editing Workload Plans

Click on the Image Modifiedicon to edit a Workload Plan entry:Image Removed

...

Removing Workload Plans

Click on the Image Modified icon to remove a Workload Plan entry:Image Removed

...

Confirm the operation:Image Removed

...


Anchor
workloadplanefficiensyassignment
workloadplanefficiensyassignment

Workload Plan efficiency

Info

If you want to simulate a non-human resource or use a single user to represent a team, you can use the efficiency multiplier. Alternatively, you can use it to reduce the capacity resulting from the Workload plan by setting a value below 1.

Anchor
assighningholidayplans
assighningholidayplans

...

When you open the page of a particular resource, you can see Holiday Plans assigned to them.Image Removed

...

Holiday Plans are sorted based on their start date (chronological): the newest items are at the top, and the oldest items are on at the bottom (regardless of the order in which items were created). 
Image Removed

...


Assigning Holiday Plans

To assign a Holiday Plan, click on the "+" icon:Image RemovedIn the pop-up box, select

...

Select a Holiday Plan name and the start date in the pop-up box. The end date will be calculated automatically based on the start date of the previous Holiday Plan (Holiday Plans can't overlap).Image Removed

...

Click the "Add" button. The Holiday Plan will be visible on the list. Image Removed

...

Info

The unspecified end date "Image Modified" will automatically change

...

when you assign a new workload plan. 

Expand

For example, if the "Interns' is supposed to last till the 1st of October,

...

you assign the "Default Holiday Plan" to start on October 1st. 
Image Modified
Image Modified

The "Interns" end date will automatically be set to the last day of September. 
Image Modified


Editing Holiday Plans

Click on the Image Modifiedicon to edit a Holiday Plan entry:Image Removed

...

Removing Holiday Plans

Click on the Image Modified icon to remove a Holiday Plan entry:Image Removed

...

Confirm the operation:Image Removed

...

Anchor
assighingabsences
assighingabsences

Absences

The list of user absences is visible on their Individuals page.Image Removed

...

Individual absences can be:

  • added by the App Admin or App Resource Admin on the Resources page.

  • added by users on their "My

    Profile

    Settings" page

    "

    . Once a user adds an Absence

    is added by a user

    , it automatically appears on the Resources page in Administration.

Absence days are automatically greyed out on the timeline as non-working days and reduce resource capacity. The App will prevent you from scheduling a task on a non-working day. 

There are five types of absences available:

  • Holiday

  • Leave at request

  • Maternity leave

  • Sick leave

  • Other reason

Absences are sorted based on their start date (chronological): the newest items are at the top, and the oldest items are on at the bottom (regardless of the order in which items were created). Image Removed

...


Anchor
ResourcesAssigningAbsences
ResourcesAssigningAbsences

Assigning Absences

To add an absence, click on the "+" icon:Image Removed

...

In the pop-up box:

  • select an absence type

  • select start + end date

  • adjust the "half-day absence in selected days toggle."  

  • you can also add a comment

  • Add another checkbox (leave empty or select)

    Image Removedimage2022-5-10_8-19-6.pngImage Added



Click the "Add" button. The absence will be visible on the list; the position on the list depends on its date (the list is chronological). Image Removed

...


Put a checkmark in Add another box if you want to add another absence right after.
Image Removed

...

Info

Absences can't overlap. If you try to add an absence, you will see a warning message at the bottom of the pop-up box. Image Removed

...


Resources module

In the Resources module, you can right-click on the resource name > Add absence to access the form.Image Removed

User-submitted absences

Info

Submitting absences by users needs to be enabled first. To enable, go to App configuration > Modules > Resources - only a Jira administrator can access this page.

Users can submit absences using using the "My Profile Settings" page. 

Half-day absences

Partial Absences can be planned for Individual Resources.Image Removed

...

Resource capacity (based on their workload plan) is halved for the absence period. 

A full day off is greyed out in the Resources module. A half-day off is not greyed out. Image Removed

...

Editing Absences

Click on the Image Modifiedicon to edit an Absence:Image Removed

...

Removing Absences

Click on the Image Modified icon to remove an Absence:Image Removed

...


Confirm the operation:Image Removed

...

Anchor
DisplayingAbsenceDays
DisplayingAbsenceDays

Displaying absence days

The absence days are greyed out like other non-working days. To see individual non-working days, using the Gantt module, click on one of the already assigned tasks.

You can enable the 'Calculate tasks automatically based on assignee's working days' option in the App administration (you need to be a Jira administrator to access this page) to show non-working days when you click on a task and allow the scheduling mechanism to reschedule your task taking into account the non-working days).