Introduction

To start working in BigPicture, you need to create a box and add tasks to this box.

It is not required for tasks to have the start and end dates defined:

  • Tasks have dates if the “Start Date” and “End Date” Start Date and End Date fields are set in Jira and the field mapping is configured. For more information, refer to the field mapping Start/end date fields article.

  • Tasks without dates (the “Start Date” and “End Date” Start Date and End Date fields are not set in Jira) can also be also added to a box in BigPicture (from the 8.19 version of BigPicture).

...

There are multiple ways to add dates to tasks without dates. You can add both dates (“Start Date” and “End Date”start date and end date) or only one of them. A task with one date is semi-transparent, as presented below:

  • No “Start Date”start date:

    Image RemovedScreenshot of a task with no start date.Image Added
  • No “End Date”end date:

    Image RemovedScreenshot of a task with no end date.Image Added

Gantt module

To add dates to a task in the Gantt module:

  1. Hover the mouse cursor over a task on the

...

  1. timeline

...

  1. .

  2. Click the

...

  1. +

...

  1. icon

...

  1. .

    Screenshot of the Gantt timeline with a task without dates.Image Modified
  2. Edit the

...

  1. Start Date and End Date fields (make sure that these columns are added to the current column view).

    Screenshot of the Gantt timeline when adding dates to a task.Image Modified

Scope module

To add dates to a task in the Scope module:

  1. Find a task.

  2. Edit the

...

  1. Start Date and End Date fields (make sure that these columns are added to the current column view).

...

Board module

...

To add dates to a task in the

...

Board module:

  1. Right-click on a task and select Edit.

  2. Complete the dates.

  3. For iterations with precise alignment

...

  1. :

    1. Move a task to such an iteration (dates to a task are added automatically based on dates for an iteration).

...

Resources module

Unscheduled tasks are visible in the sidebar on the right.

To add dates to a task in the Resources module:

  1. Expand the Unscheduled tasks panel.

  2. Drag tasks onto the grid, or double-click to edit the dates.

...

Risks module

...

To add dates to a task in

...

the Risks module:

  1. Right-click on a task and select Edit.

  2. Complete the dates.

...

Delete task dates

...

in BigPicture

You can delete dates from tasks. As a result, such tasks (without dates) disappear from the :

...

...

...

Edit task dates

...

in BigPicture

Apart from modifying the “Start Date” and “End Date” Start Date and End Date fields of a task in Jira, you can change dates by the following actions in BigPicture:

...

  • Tasks without dates and tasks where dates have been deleted are excluded from the scheduling mechanism (are considered locked tasks). Refer to the Scheduling mode (previously period mode) article.

  • Tasks with one date (“Start Date” or “End Date”start date or end date) are included in the scheduling mechanism.

Auto bottom-up mode

  • A task without dates in the scheduling mode set to auto bottom-up can get dates when dates for children tasks are added.

  • A task with dates in the scheduling mode set to auto bottom-up can lose dates when dates for children tasks are deleted.

...

Refer to the Scheduling mode (previously period mode) article.

Start date or end date set to estimate

If dates are calculated based on an estimate:

  • Setting the “Start Date” or “End Date” to a task's start or end date results in calculating the other date automatically.

  • Deleting the “Start Date” or “End Date” of a task's start or end date results in deleting the other date automatically.

Refer to the One-way sync of Start/End date article.

Auto top-down and Locked modes

  • Tasks in the scheduling mode set to auto top-down or locked can modify the dates of their children.

Task period alignment

  • When the task period alignment of a sub-scope is set to precise alignment, after adding a task to such a sub-box, the dates of a sub-box are assigned to a task automatically.

Refer to the Task period alignment article.

Conversion to milestones

Expand
titleExpand to see more

Insert excerpt
Milestones
Milestones
nameconvert-task-one-date
nopaneltrue

Constraints

Overdue tasks

Expand
titleExpand to see more

Insert excerpt
Overdue tasks
Overdue tasks
nameoverdue-tasks
nopaneltrue

Critical path

Expand
titleExpand to see more
Insert excerpt
Critical path
Critical path
namecritical-path
nopaneltrue

Dependencies

Expand
titleExpand to see more

Insert excerpt
Displaying Dependencies
Displaying Dependencies
namedependencies-task-dates
nopaneltrue

Period warnings

Expand
titleExpand to see more

Insert excerpt
Period warnings
Period warnings
nameperiod-warnings-dates
nopaneltrue

Baselines

Expand
titleExpand to see more

Insert excerpt
Baselines
Baselines
namebaselines-task-dates
nopaneltrue