You can assign your resources to predefined Skills, Workload Plans, and Holiday Plans or plan Absences in this view.

Security and access

  • Only a person with the App Admin and App Resource Admin security role can access this page.
  • To assign resources go to Administration > Resources > Individuals > click the resource name.

Image Modified

Current assignment

In Resource manager, at the top of a page of a given resource, you can see their current Absences, Holiday Plans, Workload Plans, and Skills:
Image Modified

The timeline on the right helps you visualize Absences, Holiday Plans, and Workload Plans:
Image Modified

Additionally, current items can be highlighted (yellow) if the Highlight present data option on a timeline is selected

Image Modified

Timeline navigation

FeatureDescription
Scroll

When you hover your mouse over the timeline, hold Shift and scroll using the mouse wheel. 
OR
Image Modified

You can scroll 10 years in each direction.


Image Modified

The "Today" button centers the view on the present date. 
Image Modified

Image Modified

Zoom out.

Image Modified

Zoom in. 

Image Modified

Display options pop-up menu: allows you to show/hide week numbers on the timeline.
Image Modified
Image Modified

Image Modified

Applicable to the entire page (including sections below the timeline). 

View options allow you to hide/display items based on their relation to the present day. 

Image Modified

Highlight present data - when selected, items currently relevant are highlighted in yellow.
Image Modified


Teams

Total team assignment of a resource (across all Boxes) can be reviewed on the resource details page. 

Image Modified

Team assignment (availability, period, etc.) has to be edited in a Box where it has been added. This information is in the created in column. Listed items work as links that take you to the Box in question.
Image Modified

Related to column contains info about what sub-Boxes are affected by team assignment → click on the number to see a pop-up containing the list of Boxes that inherited the assignment. The ID column works as a link to a given Box.

Image Modified

Skills

Image Modified

In order to assign a resource to a skill, the App admin need to define the skills first in the App's administration. Each skill has a start date (required field) and end date. Resources can be assigned to multiple skills at the same time.

The order of the listed Skills is sorted by the end date, then by the start date (oldest "end date" skills at the bottom, newest at the top. If the end date is the same, oldest "start date" at the bottom, newest start date at the top).
Image Modified

Once assigned, the new skill will be visible in the Resources module when the Skill panel is enabled.

Assigning Skills

To assign a skill click on the "+" icon:
Image Modified

In the pop-up box, select a skill name and the timeframe for the skill assignment:
Image Modified

Click the "Add" button. The skill will be visible on the list. 
Image Modified

Editing Skills

Click on the Image Modifiedicon to edit a skill entry:
Image Modified 

A details pop-up will appear. After making adjustments, hit "Save". 
Image Modified

Removing Skills

Click on the Image Modified icon to remove a skill:
Image Modified

Confirm the operation:
Image Modified

Anchor
assigningworkloadplans
assigningworkloadplans

Workload plans 

Resources can be assigned to multiple workload plans but not at the same time. The App admin can define the workload plans in the App's administration. When assigning a resource to a workload plan, both start and end dates are required and the App will automatically set the end date when a new plan is added. 
Image Modified

Workload Plans are sorted based on their start date (chronological): the newest items are at the top and the oldest items are on the bottom (regardless of the order in which items were created). 
Image Modified

Assigning Workload Plans

To assign a Workload Plan click on the "+" icon:
Image Modified
In the pop-up box, select a Workload Plan name and the start date. The end date will be calculated automatically based on the start date of the previous Workload Plan (Workload plans can't overlap).
Image Modified 
Click the "Add" button. The Workload plan will be visible on the list.
Image Modified 


Info

The unspecified end date "Image Modified" will automatically change, when you assign a new workload plan. 

Expand

For example, if the "crunch' is supposed to last till the 1st of June, assign the "Default Workload Plan" to start on June 1st. 
Image Modified
Image Modified

The "crunch" end date will automatically be set to the last day of May. 
Image Modified


Editing Workload Plans

Click on the Image Modifiedicon to edit a Workload Plan entry:
Image Modified

Removing Workload Plans

Click on the Image Modified icon to remove a Workload Plan entry:
Image Modified

Confirm the operation:
Image Modified

Anchor
workloadplanefficiensyassignment
workloadplanefficiensyassignment

Workload Plan efficiency

Info

If you want to simulate a non-human resource or use a single user to represent a team, you can use the efficiency multiplier. Alternatively, you can use it to reduce the capacity resulting from the Workload plan by setting a value below 1.

Anchor
assighningholidayplans
assighningholidayplans

Holiday plans

You can create Holiday Plans in the "Holiday Plans" tab in the App's administration. 

When you open the page of a particular resource, you can see Holiday Plans assigned to them.
Image Modified

Holiday Plans are sorted based on their start date (chronological): the newest items are at the top and the oldest items are on the bottom (regardless of the order in which items were created). 
Image Modified

Assigning Holiday Plans

To assign a Holiday Plan click on the "+" icon:
Image Modified

In the pop-up box, select a Holiday Plan name and the start date. The end date will be calculated automatically based on the start date of the previous Holiday Plan (Holiday Plans can't overlap).
Image Modified

Click the "Add" button. The Holiday Plan will be visible on the list. 
Image Modified

Info

The unspecified end date "Image Modified" will automatically change, when you assign a new workload plan. 

Expand

For example, if the "Interns' is supposed to last till the 1st of October, and you assign the "Default Holiday Plan" to start on October 1st. 
Image Modified
Image Modified

The "Interns" end date will automatically be set to the last day of September. 
Image Modified


Editing Holiday Plans

Click on the Image Modifiedicon to edit a Holiday Plan entry:
Image Modified

Removing Holiday Plans

Click on the Image Modified icon to remove a Holiday Plan entry:
Image Modified

Confirm the operation:
Image Modified

Anchor
assighingabsences
assighingabsences

Absences

The list of user absences is visible on their Individuals page.
Image Modified

Individual absences can be:

  • added by the App Admin or App Resource Admin on the Resources page.
  • added by users on their "My Profile page". Once an Absence is added by a user, it automatically appears on the Resources page in Administration.

Absence days are automatically greyed out on the timeline as non-working days and reduce resource capacity. The App will prevent you from scheduling a task on a non-working day. 

There are five types of absences available:

  • Holiday
  • Leave at request
  • Maternity leave
  • Sick leave
  • Other reason

Absences are sorted based on their start date (chronological): the newest items are at the top and the oldest items are on the bottom (regardless of the order in which items were created). 
Image Modified

Anchor
ResourcesAssigningAbsences
ResourcesAssigningAbsences

Assigning Absences

To add an absence, click on the "+" icon:
Image Modified

In the pop-up box:

  • select an absence type
  • select start + end date
  • adjust the "half-day absence in selected days toggle"  
  • you can also add a comment
  • Add another checkbox (leave empty or select)
    Image Modified

Click the "Add" button. The absence will be visible on the list; the position on the list depends on its date (the list is chronological). 
Image Modified

Put a checkmark in Add another box if you want to add another absence right after.

Image Modified

Info

Absences can't overlap. If you try to add an absence you will see a warning message at the bottom of the pop-up box. 
Image Modified

Resources module

In the Resources module, you can right-click on the resource name > Add absence to access the form.

Image Modified

User-submitted absences

Info

Submitting absences by users needs to be enabled first. To enable go to App configuration > Modules > Resources - only a Jira administrator can access this page.

Users can submit absences using My Profile page. 

Half-day absences

Partial Absences can be planned for Individual Resources.

Image Modified

Resource capacity (based on their workload plan) is halved for the absence period. 

A full day off is greyed out in the Resources module. A half-day off is not greyed out. 

Image Modified

Editing Absences

Click on the Image Modifiedicon to edit an Absence:
Image Modified

Removing Absences

Click on the Image Modified icon to remove an Absence:
Image Modified

Confirm the operation:
Image Modified

Anchor
DisplayingAbsenceDays
DisplayingAbsenceDays

Displaying absence days

The absence days are greyed out like other non-working days. To see individual non-working days, using the Gantt module, click on one of the already assigned tasks.

You can enable the 'Calculate tasks automatically based on assignee's working days' option in the App administration (you need to be a Jira administrator to access this page) to show non-working days when you click on a task and allow the scheduling mechanism to reschedule your task taking into account the non-working days).