Skip to end of banner
Go to start of banner

Holiday Plans

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 2 Current »

Introduction

You can create holiday plans to reflect holidays and observances. Each non-working day resulting from the holiday plan reduces the capacity (daily capacity to zero) of the assigned resource or the team.

Tasks can be calculated automatically based on the assignee’s working days.

Holidays can be grouped into a set, such as European holidays. If the organization also has offices in the United States, a holiday set can be created for that region as well. The planning process is improved as information is easily accessed across the organization.

Security and access

App admins and App resource admins can access the Holiday plans page:

  1. Open BigPicture.

  2. Click the wrench button on the right side.

  3. Select Resources.

 See the screenshot

  1. Navigate to the Holiday plans tab.

Holiday modes

The table below presents the available modes:

You can view all holidays and inline edit the holiday name field.

Holiday mode

Description

Non-working days

The non-working days of the week are marked with a grey color circle.

Floating holidays

Dates are NOT moved to the next year automatically and are marked with a blue color circle.

Fixed holidays

Dates are automatically moved to the next year and are marked with a red color circle.

Extra working days

The extra days are marked with a white color circle.

Default holiday plan

When a task is added to the scope of a box, or when the currently assigned plan is deleted, the task assignee is automatically assigned to the default holiday plan.

You cannot delete default holiday plans.

Add new holiday plans

To create a holiday plan:

  1. Go to the Holiday plans page.

  2. Click Add new plan.

  3. Provide:

    • Name

    • Code (max. 10 characters)

  4. Click Add to confirm.

Edit the calendar

To view and edit holiday dates:

  1. Go to the Holiday plans page.

  2. Click:

    • the name of the plan, or

    • the Details button

  3. Click Edit details to start making changes.

  4. Click the date you want to convert to a holiday and select the mode:

    • Extra working day

    • Fixed holiday

    • Floating holiday

  5. Click Save.

  6. If necessary, define non-working days on the left side of the screen.

  7. Click Save changes to confirm.

Use the arrows in the top-right corner to move the calendar to the next year.

Delete holiday plans

To delete a holiday plan:

  1. Go to the Holiday plans page.

  2. Click the Delete button:

    • on the holiday plans overview page, or

    • on the holiday plan details page

Resources assigned to a deleted plan are assigned to the default holiday plan instead.

Non-working days

Holiday plans allow you to define non-working days, which define company-wide, religion-specific, or national holidays.

Scheduling impact

Non-working days resulting from holiday plans directly impact automatic task scheduling.

  • No labels