Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Respect Jira screen scheme

Warninginfo

This functionality is available only in the Server version of the App. The following section doesn't apply to cloud users - the screen scheme is always automatically respected in the cloud version of the App. More information on the differences between cloud and server versions of the App can be found here.toggle switch will NOT stop the App from updating Jira values.

It only prevents you from changing the value in the App when it cannot be properly reflected in Jira. 

The "Respect Jira screen scheme" toggle switch applies to start/end date field mapping.

...

titleField mapping (start/end date)

Bi-directional sync:

App → Jira

When you move a task on the Gantt chart, → you change the start/end date of a task → you change the values of the mapped fields.
If "End date" is mapped to "Due date," → changing the "End date" on the Gantt chart → changes the value of the "Due date" field in Jira.

Jira → App

When you update a field in Jira, → you change the start/end date of a task → you move the task on the Gantt timeline.
If "End date" is mapped to "Due date," → changing the "Due date" in Jira → changes the value of the "End date" on the Gantt timeline.

Remember, both "Start date" and "End date" can reflect a selected Jira field.

Image Removed

For example, "End date" can be mapped as "Due date."

Image Removed

to all fields

Toggle switch off:

Bi-directional sync (of start/end date) is not required but will be performed when possible. 

Even when fields mapped as start/end date cannot be updated by the App (because they haven't been added to the project's Jira screen scheme), you can still freely move tasks on the Gantt chart, etc. - even though a Jira field cannot reflect those changes, you still can make them in the App. The bi-directional sync isn't required - it's performed when possible, but when it can't be done, the App still lets you change the start/end date.

The toggle switch on:

Bi-directional sync (of start/end date) is required. When the toggle switch is on, the App lets you change the start/end date field value of a task only if it can be reflected in Jira.

Info

This toggle switch will NOT stop the App from updating Jira values. It only prevents you from changing the start/end date in the App when it cannot be properly reflected in Jira. 

...

When a field isn't available for a Jira issue, you can't edit it in BigPicture. 

Exception - Mapped fields

Even when mapped fields cannot be updated by the App   (because they haven't been added to the project's Jira screen scheme),   you can 't change the start/end date in the App. If a field doesn't exist in your Jira project, the App cannot perform still edit them in BigPicture. The bi-directional sync and blocks you from changing the start/end date. You can't move a task on the Gantt timeline because the App can't update Jira field values to reflect start/end date changes. 

When setup is complete (the fields selected for start/end date mapping exist in a Jira project), the App can perform bi-directional sync without problems. The fields mapped as start/end dates are updated accordingly.

Info

Exception: Time Spent + Remaining Estimate and Original estimate

Time Tracking can be used for start/end date mapping, but the expected behavior is different.

Image Removed

Affects

The "Respect Jira screen scheme" toggle switch applies to start/end date field mapping.

Limitations

The App verifies if the option "Respect Jira's Screen scheme" configuration is enabled for the project to which the selected task belongs. 

If the option is enabled, the App verifies if the field is on the project scheme before trying to update the field.

If the field is not present on the scheme, then the App does not overwrite it and a warning message is displayed.

Jira Cloud only

The App verifies if the option "Respect Jira's Screen scheme" configuration is enabled but also additional check isn't required - it's performed when possible.

Image Added

Save task updates as comments

...

To learn more about absence days, go to Assigning Resources.

Overwrite Jira task data with data from the App

The “Overwrite Jira task data with data from the App” option can be switched on when you change the “Start date” or “End date” to a different field than the one currently used.

...