This section changes the task field synchronization settings and enables additional features such as comments and notifications, which facilitate communication within teams.

...

  • Only Jira administrators can access this page.
  • To configure the fields synchronization, go to App Configuration > General > Fields.

General mapping

Info

You cannot use the same field more than once. For example: If the "Due Date" field is mapped as the "End Date" of your task, you will not be able to select this field for any other mapping within a configuration of the same Jira Project. This applies to the following filed mappings:

  • Start Date
  • End Date
  • Baseline Start Date
  • Baseline End Date

...

Each instance connection can be expanded. Upon expanding, you can see the field mapping settings of the particular instance.

Overwrite Jira task data with data from the App

The “Overwrite Jira task data with data from the App” option can be switched on when you change the “Start date” or “End date” to a different field than the one currently used.

...

Customize your synchronization settings by creating a separate configuration scheme for a Jira project. When you do that, general settings will no longer apply to this project.