Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

...

...

...

...

...

...

...

Table of contents:

Table of Contents
minLevel1
maxLevel6
outlinefalse
styledefault
typelist
printablefalse

Respect Jira screen scheme

Warninginfo

This functionality is available only in the Server version of the App. The following section doesn't apply to cloud users - the screen scheme is always automatically respected in the cloud version of the App. More information on the differences between cloud and server versions of the App can be found here.toggle switch will NOT stop the App from updating Jira values.

It only prevents you from changing the value in the App when it cannot be adequately reflected in Jira. 

The "Respect Jira screen scheme" toggle switch applies

...

titleField mapping (start/end date)

Bi-directional sync:

App → Jira

When you move a task on the Gantt chart, → you change the start/end date of a task → you change the values of the mapped fields.
If "End date" is mapped to "Due date," → changing the "End date" on the Gantt chart → changes the value of the "Due date" field in Jira.

Jira → App

When you update a field in Jira, → you change the start/end date of a task → you move the task on the Gantt timeline.
If "End date" is mapped to "Due date," → changing the "Due date" in Jira → changes the value of the "End date" on the Gantt timeline.

Remember, both "Start date" and "End date" can reflect a selected Jira field.

Image Removed

For example, "End date" can be mapped as "Due date."

Image Removed

to all fields

Toggle switch off:

Bi-directional sync

...

is not required but will be performed when possible. 

...

The toggle switch on:

Bi-directional sync

...

is required. When the toggle switch is on, the App lets you change the

...

field value of a task only if it can be reflected in Jira.

...

Info

This toggle switch will NOT stop the App from updating Jira values. It only prevents you from changing the start/end date in the App when it cannot be properly reflected in Jira. 

When fields mapped as start/end date When a field isn't available for a Jira issue, you can't edit it in BigPicture. 

Exception - Mapped fields

Even when mapped fields cannot be updated by the App   (because they haven't been added to the project's Jira screen scheme),   you can 't change the start/end date in the App. If a field doesn't exist in your Jira project, the App cannot perform still edit them in BigPicture. The bi-directional sync and blocks you from changing the start/end date. You can't move a task on the Gantt timeline because the App can't update Jira field values to reflect start/end date changes. 

When setup is complete (the fields selected for start/end date mapping exist in a Jira project), the App can perform bi-directional sync without problems. The fields mapped as start/end dates are updated accordingly.

Info

Exception: Time Spent + Remaining Estimate and Original estimate

Time Tracking can be used for start/end date mapping, but the expected behavior is different.

Image Removed

Affects

...

isn't required - it's performed when possible.

...

Save task updates as comments

You can add task updates made using the App as Jira comments. Depending on your Jira settings, users Users can get notifications when a task is updated via the App depending on their Jira settings.

Info

Working with the Gantt module may update multiple dependent tasks with a single operation, which will result resulting in numerous notifications if this option is enabled.

Such updates may also occur when the scope of the box is defined.

...

Send "Issue updated" notification after task updates

When enabled, the "Issue Updated" notification will be sent to users unless the users do not have the permissions permission to send notifications.

If notifications are not configured while this feature is enabled, only admin users will get notified.

Auto recalculation based on the assignee's working days

If a task is assigned to an individual resource, its period will always be automatically calculated based on the assignee’s working days, and the default Working schedule is ignored.

To learn more about absence days, go to Assigning Resources.

...

Overwrite Jira task data with data from the App

The “Overwrite Jira task data with data from the App” option can be switched on when you change the “Start date” or “End date” to a field different from the one currently used.

As a result, Jira task data is overwritten with data from BigPicture. This action is irreversible.Image Removed

...