How to update release

...

  1. Navigate to Swanly via Apps > Swanly Roadmaps

  2. Open release report panel by clicking on the activity name in the roadmap or list view

  3. In the report panel, click on a field (release attribute) that you want to update

  4. Update the attribute

  5. Click on the Checkbox icon to save or Cross icon to cancel the changes

...

  1. In the report panel, click on a Release start date or Release end date - a calendar modal will appear

  2. Click on the desired date - changes will be saved automatically

  3. Click on Edit stage dates to reschedule release stages