Introduction

To assess the performance of the project over time, you can set baselines and track deviations from the initial schedule.

Baselines can be synchronized with Jira. The synchronized fields can be added to the column views.

You can create and delete baselines for all the tasks in the scope of the box or selected tasks only. Baselines are displayed as bold lines and show the position of the task at the moment of creating the baseline.

...

By default, the Baseline start date and Baseline end date custom fields are selected. The fields are created during the BigGantt installation.

Enable synchronization

A Jira admin can synchronize baselines with Jira:

  1. Open BigGantt.

  2. Click the wrench button icon in the top-right corner.

  3. Select General.

  4. Navigate to the Fields section.

  5. Find:

    • Baseline start date field

    • Baseline end date field

  6. Select fields from the drop-down menu to synchronize with.

  7. Click Save to confirm.

Disable synchronization

A Jira admin can disable the synchronization of baselines with Jira:

  1. Open BigGantt.

  2. Click the wrench button icon in the top-right corner.

  3. Select General.

  4. Navigate to the Fields section.

  5. Find:

    • Baseline start date field

    • Baseline end date field

  6. Select the Not Synchronized option for both fields.

  7. Click Save to confirm.

Baseline fields in column views

...