Change log in Gantt module
...
Category | Feature description | Sneak peek |
---|---|---|
Navigation and layout | Navigating to scope definition When there's nothing to display, splash screens in the modules (Gantt, Scope, Board, Resources, Calendar) provide direct access to scope definition. | |
Scope definition The "Manually Added Tasks" section is available only when it contains at least one task. | ||
Scope module - "Delete" button (viewer permissions limitations) The "delete" button on the Scope module is hidden for the Box viewer. | ||
Scope module - drag-and-drop (viewer permissions limitations) The drag-and-drop option is not available to the Box viewer, as they are not allowed to change the task structure. | ||
Scope module - column aggregations (viewer permissions expanded) Box viewer can change aggregations column aggregations. | ||
Risks module - risk matrix view settings Risks matrix view settings are saved per user. The same settings are propagated to all the boxes a user has access to. | ||
Scheduling | Tasks in the "auto top-down" period mode are scheduled on Working Days The app recognizes weekends and other days off and moves a task to accommodate them. | |
Usability | Gantt module - greyed-out tasks can be hidden When you apply filters, the Gantt tasks structure can be displayed as a flat structure, where parent (greyed) tasks are hidden. | |
Board module - greyed-out tasks can be hidden Backlog of the Board module - task structure can be displayed as a flat structure, where parent (greyed) tasks are hidden. | ||
Critical path | The Critical Path does not include tasks that are not immediate neighbors
| |
Scope cloning | Original estimate values are copied during the cloning process | |
Scope definition | You can select a task structure template:
Custom settings are still available. | |
Task structure - manual changes Clear just the changes that were manually made to the task structure. The structure that was based on the structure builders is not affected. | ||
RETIRED - Manually removed tasks section no longer available Manually removed task → task moved from one Box with scope type set to "Own" to another with the scope type also set to "Own." Moving a task between different own scopes is not possible - drag and drop is disabled on the Board module. The manually removed tasks section was removed from the scope definition screen. Existing manually removed tasks are still in effect). |
...