Introduction

The timeline adjusts dynamically to match Timebox dates (in this case, Timeboxes are called Program Increments or Iterations). It allows you to add Markers that represent important events by simply clicking on the timeline.

...

For example, markers can represent milestones. 'Milestones are used to track progress toward a specific goal or event. There are three types of SAFe milestones: Program Increment (PI), fixed-date, and learning milestones.' © Scaled Agile, Inc.

...

Timeline

The Timeline begins at the start date of the earliest Timebox on the Board and ends together with the end date of the latest Timebox.

Current date

...

true

About the timebox timeline and markers

The Board module visualizes project timeboxes (Program Increments, Sprints, or Iterations) on a horizontal timeline. You can add date markers to the timeline to highlight important events on your timeline, like milestones or stakeholder meetings.

...

Timeline

The timeline starts at the earliest timebox's start date on the board and ends with the latest timebox's end date.

Navigation arrows

The arrows on the left and right sides allow you to move backward or forward one timebox at a time.

Today button

Click this the Today button to immediately move the timeline to the current Program Increment or Iteration (if such a timebox exists).

Zoom in /

...

zoom out buttons

You can zoom Zoom in or zoom out to change the number of Program Increments or Iterations displayed at the same timeon the board. You can display up to seven timeboxes on the board. The maximum number of elements you can display is 7 and it depends on your screen resolution (above 2400 pixels width).

Markers

Info

The marker functionality can also be found in the Gantt, Board, and Roadmap modules. To learn more, visit the page about Markers.

Markers can indicate important events on the timeline, such as dates or milestones.

You can add and edit them using the Gantt, Board, and Roadmap modules. To learn more, go to Markers.

...

:

  • show a list of markers on a selected date,

  • create a new marker,

  • edit the existing marker,

  • delete the existing marker

directly on the board timeline.

...