Introduction

The BigPicture Gantt module comes in handy to visualize your project roadmap.

The Gantt module includes four key elements:

  • Customizable task list (Work Breakdown Structure - WBS).

  • Timeline with a high-level overview of the entire project, with tasks and dependencies that visualize your work items and include auto-scheduling.

  • Resources panel that shows your resources’ workload. You can easily notice over and under-allocation of resources.

  • Infobar that highlights the most important information related to your project, e.g. Overdue tasks, Critical path, Dependencies, and Milestones.

All these elements empower the way your roadmap is presented. Let the Gantt module develop high-level roadmaps for you.

See the video:

https://fast.wistia.com/embed/medias/o16tm0s3g2.jsonp

Visualize relations between items

Let’s use BigPicture to enable cross-project management for dependencies among items from different monday boards. BigPicture provides a number of automation mechanisms that help you save time and keep hundreds of tasks under control and within deadlines. BigPicture allows you to automate task scheduling and create dependencies between items from various monday boards.

Dependencies are relationships between tasks, milestones, and other items. The mechanism can simultaneously move one or more tasks linked to a task that is being moved. By defining dependencies, task dates and other initiatives are updated automatically as a result of changes made to a project.

BigPicture can schedule the task based on dependencies, task structure, and other factors. There are five different modes:

  • Auto basic (default mode)

  • Auto bottom-up

  • Auto top-down

  • Manual

  • Locked

See the video:

https://fast.wistia.com/embed/medias/tlwmny5gil.jsonp

Map dependencies and monitor progress

Keep your tasks on track with auto-scheduling

Dependencies specify the relationship between items, milestones, and other elements in a logical sequence. They help you visualize the order in which you need to proceed with the issues and estimate the timeframe. You can draw dependencies between parent items and sub-items in the same monday board, as well as items from different monday boards.

2023-11-06_13-26-03.mp4

Dependencies

Soft dependencies

In BigPicture, No action dependencies are called Soft dependencies and are used to mark relationships between tasks without changing their dates (indicating that tasks are thematically related). You can also create dependencies between items from different monday boards.

Soft dependencies are marked on the Gantt chart with a dashed line.

Strong dependencies

In BigPicture, Strict and Flexible dependencies are called Strong dependencies and they can cause task date changes, as they are mainly used for scheduling.

BigPicture provides great possibilities for defining four types of dependencies, setting them in ASAP or non-ASAP mode, as well as adding a time interval between tasks (called “lag time”). You can also create dependencies between items from different monday boards.

Strong dependencies are marked on the Gantt chart with a solid line.

Lag time 

It is the time period calculated in days by dividing the linked tasks. Lag time has the highest priority over other dependency properties. In both ASAP and non-ASAP modes the lag time will be respected and applied regardless of other circumstances. The type of dependency determines which date (Start or End) of the source task the lag time will be added to.

ASAP mode

ASAP mode always schedules the target task to take place “as soon as possible”, according to dependency type. This renders the target task strictly dependent on the source. Therefore, it will be impossible to drag and drop it, neither to the future nor the past. The target task will always revert to its position previously calculated by scheduling.

Dependencies in monday vs. BigPicture

Dependencies existing on the monday side, as well as on the BigPicture side will run parallel scheduling mechanisms affecting task dates. If monday board has a column with Strict or Flexible dependencies, this means that dependencies in BigPicture should NOT then affect tasks. Otherwise, various scheduling mechanisms would lead to setting incorrect dates on tasks.

Customize the timeline view to track progress

With the timeline options, you can easily monitor progress and deadlines. The features, such as milestones and markers, provide a clear visual representation of project progress. The timeline can be modified to display various time intervals depending on your needs.

2023-11-06_11-27-24.mp4

Make “what-if” scenarios to test changes to the Gantt chart

If you wish to take your planning activities to the next level, use the what-if scenario option and try out different variants of your plan, compare the results, or save your scenario as reference points. The scenarios don’t make any changes in your monday items until you decide to replace the live view with it.

2023-11-06_11-44-39.mp4

Organize your tasks in a way you need

Display different fields as columns, change the aggregation, and display options

You no longer need to go to a given issue separately to check its details. With BigPicture, you get a holistic view of your project at once. You can freely customize the task tree in the Gantt module in terms of the data you want to see. Column views allow you to add various fields and configure their display and aggregation settings in just a few clicks. Once your column view is customized, you can save it for future use.

2023-11-06_11-52-23.mp4

Control critical paths and set milestones

Generate the critical path for your project

Don’t spend time calculating the critical path on your own. Let BigPicture take care of it for you! As long as you have your scope and strong dependencies, BigPicture will automatically draw the critical path. You can also create alternative critical paths with what-if scenarios.

2023-11-06_13-31-47.mp4

Use drag & drop and inline editing

Arrange everything with drag & drop

The drag & drop feature allows you to perform various actions in BigPicture such as moving boxes up and down in the hierarchy, creating dependencies, moving the timeline, and much more!

Update fields with inline editing

Instead of jumping between several edit pages, use theinline editing option to make changes to tasks. Discover how easy it is to inline edit fields when working with column views or grouping tasks.