Introduction
A defined collection of tasks makes up the box scope. In general, tasks can be added to the scope manually or get automatically synchronized with connected tools such as Trello.
Security and access
To access the Scope definition section at the box configuration level:
Method 1:
Open BigPicture.
Navigate to the Overview module.
Find a box.
Click the More actions button on the right side.
Click Configure.
Expand the Tasks section and navigate to Scope definition.
Method 2:
Go to the Gantt module.
Expand the Add task icon visible in the top-left corner below the box name.
Select the Manage scope definition option.
Depending on the box hierarchy and the scope type of a given box, the sections on the Scope definition page differ (every box type has the Scope definition page in box types settings). A box with two levels of sub-boxes shows all possible sections.
Scope definition elements
The table below presents elements and actions you can perform on the Scope definition page.
Scope definition element or action | Description |
---|---|
Scope of the context box |
|
Scope of the sub-boxes |
|
Switch between levels of child boxes | Using the arrows you can switch between viewing the level of children and grandchildren in a given box. |
Basic info and status of child boxes | Click the … icon to:
|
Own scope
Box admins can:
define the automatic rules to pull in tasks (from connected tools).
view and erase them from the scope manually.
The quickest way to set up the scope is to use the automatic rules.
Own scope - set automatic rules
Role or element | Description |
---|---|
Scope owner |
|
Scope filters |
|
Own scope - set rules manually
Element | Description |
---|---|
Manually added tasks |
|
Manually removed tasks |
|
Task types |
|
Sub-scope
Boxes with sub-scope display tasks added to a higher-level box with own scope. Any task added to a box with a sub-scope is automatically added to an upper-level box with own scope.
You can use the field value synchronization to assign tasks to boxes with sub-scope. Whenever you add a new task while working with a sub-box, you are assigning tasks to the upper-level box.
There are three columns for each box in the sub-boxes section:
Name - the name of the tool with source data, such as a Jira instance, or connected tool, such as Trello.
Field - the field used to synchronize with Jira. You can use the following field types: string, text, Jira epic link, and select list (single choice).
Value - the field value used to identify a task in a given box.
When synchronizing with a sprint field, the search only finds the given sprint on the board where it was created. The correct board should be selected using the filter before searching for a sprint.
Reuse a field value in multiple boxes
You can reuse a field value (the same field value can be used for the synchronization of more than one box), but each time it should apply to a different set of tasks.
The warning message
If BigGantt recognizes that a task is already in more than one box with own scope and there are clashing configurations within the sub-scope definitions:
Sub-scope field sync is stopped for a task (existing values of sub-scope sync fields are NOT cleared).
Limitations
You cannot reuse a field value for sub-scope sub-boxes of the same own scope box. Otherwise, BigGantt cannot sort the tasks from own scope into sub-boxes, because the same task cannot be at the same time in multiple sub-boxes.
Security roles in sub-scope boxes
Users of sub-boxes with sub-scope can make any changes that match their permissions in a given sub-box, even if they lack appropriate permissions to their own scope box.
Available operations:
Create tasks
Add tasks to own scope as manually added
Delete tasks
View tasks
Timeboxes
Timeboxes define consecutive time frames used for work planning. It helps to think of them as, e.g., sprints, iterations, increments, or stages.
You can configure each row separately, use the same value for each row or leave the fields empty. Configuration of the next sequential sub-box is based on its predecessor. No additional patterns are taken into account.
BigGantt configures scope synchronization of sub-boxes within a particular box based on the setup of the last sequential, same-level sub-box.
The Next timebox template toggle switch has to be activated.
Action | Description |
---|---|
Auto sprint creation | When you create a new timebox (such as program increment or iteration), BigGantt can create a corresponding sprint. The auto-configuration option configures the scope definition of newly added and existing but NOT configured timeboxes. The process takes place once one of the following actions is performed:
|
Sprint vs box duration | Sprint and box periods are NOT synchronized or related in any way. |
New sprint vs existing sprint assignment | Synchronization of sprints with boxes works in two steps - if a sprint already exists, it is synchronized with a newly created box (a new sprint is NOT created unless no matching sprint has been found). Toggle switch activation - when a new timebox has been created, the setup of the last existing timebox is used to create the next one:
To change the sprint naming scheme, you have to first change a sprint name in Jira, and then associate it with the last timebox. Otherwise, BigGantt ignores the existing sprint with a name that does not match the last timebox, and a new sprint that meets the specifications is created. |
Save scope
BigPicture validates the scope. In case of errors, saving the scope fails.
If you define the scope correctly (all tasks exist and filters are NOT corrupted), the total number of tasks is displayed.
You cannot save the scope when:
At least one item in the scope definition is incorrect or does NOT exist.
The total number of tasks is greater than the task limit set for boxes.
Duplicated tasks
When a task is added manually and updated so it fits the filter described in the Automatic rules section, it is classified as a duplicate.
Refresh cache
The Refresh cache option on the scope definition page is available on Jira Cloud.
Use the Refresh cache option when you cannot find the project, board, or quick filters on the scope definition page. After pressing the Refresh cache button, the screen is disabled for 5 seconds. The option refreshes only projects, boards, and quick filters.
Recalculate box scope aggregations
Set the time interval in which BigPicture recalculates box scope aggregations. The smaller the value, the higher the performance load for BigPicture. The recommended time is 60 seconds.
Open BigPicture.
Click the wrench button on the right side.
Select Modules.
Navigate to the Overview tab.
Set the time interval in the Box scope aggregation field.