both the source and the target space must be selected together to be migrated to Cloud
Comala Publishing migration will only be fully completed if both the source and the target space are migrated to Cloud.
pages with restrictions identified in the Atlassian Migration Assistant App vendor checks screen must have the restrictions removed prior to migration
if the publishing configuration in Data Center/Server includes conditions not supported in Cloud such as Copy label, publishing status for these pages may differ once migrated to Cloud
When migrating Comala Publishing from server to cloud, if you choose to migrate pages with restrictions, migration now sets the page publishing status in the source space to NEW if a source page or the linked target space page have page restrictions. This avoids misaligning the publishing status for these pages in the cloud spaces.
The server/data center license is not transferable to cloud.