After adding a project into Swanly roadmap, it's necessary to have the start and end dates assigned to the issues. Otherwise, the roadmap will display just the project list. Please, check the process to add start and end dates to the issues.
To do it,Â
Access Swanly via Apps > Swanly Roadmaps
Choose the issue roadmap you wish to work with from the dropdown
Click on the button + ADD ISSUE located on the hand-right in the top corner.
After doing this process, you should be able to see the issues on the Swanly issue roadmap.Â