Managing Overdue Tasks in BigPicture: Custom Status and Built-in Tracking Features

Managing Overdue Tasks in BigPicture: Custom Status and Built-in Tracking Features

This article addresses multiple use cases for tracking delayed work:

  • Scenario 1: Adding a custom "Overdue" status to a Jira workflow to be reflected in BigPicture.

  • Scenario 2: Using built-in BigPicture indicators and columns to highlight overdue tasks without changing workflows.


Scenario 1: Adding a Custom "Overdue" Status to the Workflow

If your organization requires a formal "Overdue" status in the task lifecycle, you must configure this in Jira. BigPicture reflects the Jira workflow and does not maintain a separate set of statuses.

Context

The user wanted to add an "Overdue" field to their standard workflow (Pending, In Progress, In Analysis, Completed) and apply it across all Box types (Agile, Classic, Hybrid, etc.).

Solution

  1. Jira Configuration: A Jira Administrator must add the "Overdue" status in Jira Administration > Workflows.

  2. Mapping: Jira uses three fixed status categories: To Do (Gray), In Progress (Blue), and Done (Green). Any new status must be mapped to one of these.

    • Note: An "Overdue" status mapped to "In Progress" will appear blue in BigPicture.

  3. Visibility: Once added to the Jira workflow scheme, the status automatically appears in BigPicture across all Box types using that scheme.


Scenario 2: Using Built-in Overdue Tracking (Recommended)

BigPicture provides automated tools to visualize delays based on task end dates. This method is recommended as it requires no workflow changes and provides better visual highlighting.

Context

The user wanted to highlight overdue tasks in the task list and timeline.

Solution: Highlighting Overdue Tasks

BigPicture offers three main ways to track delays automatically:

1. Overdue Task Indicators on Gantt Timeline

You can enable color-coding directly on the Gantt chart timeline:

  • Red: Task is >7 days overdue.

  • Yellow: Task is 3–7 days overdue.

How to enable (New Navigation):

  1. Open the Gantt module.

  2. In the top toolbar, click Indicators.

  3. Toggle on the Overdue tasks option.

Note: In older versions of BigPicture, this setting was located under View > Task indicators.

2. Overdue Columns in Task List

You can add specific data columns to your Gantt or Scope view to see the exact delay:

  • Overdue (End Date): Displays the number of days past the scheduled end date.

  • Overdue (Start Date): Displays the number of days past the scheduled start date.

How to add columns:

  1. Click the Columns (cog icon) in the task list header.

  2. Search for "Overdue".

  3. Select the desired field to add it to your view.

3. Infobar Overdue Report

The Infobar provides a consolidated list of all delayed tasks.

  1. Open the Infobar (right-hand sidebar) in the Gantt module.

  2. Select the Overdue report icon.

  3. The list will show all tasks past their end date, sorted by the length of the delay.


Related Articles