Understanding BigPicture Resources Module: Capacity and Team View Calculations

Understanding BigPicture Resources Module: Capacity and Team View Calculations

Use this guide when customers ask how BigPicture Resources values are calculated, especially entries such as 0.8H / 40.0H, team workload totals, and whether values apply to a specific box or the full Jira instance.

Best use case: Documentation-style support questions from evaluators or customers who want clarification on the Resources module behavior in BigPicture Cloud.

When to use this response pattern

  • Customer asks what the first value in a resource capacity display means

  • Customer wants to know whether logged time is calculated for the current Program/Project only or the whole Jira instance

  • Customer asks how Team view totals are calculated

  • Customer requests supporting documentation for the Resources module

Core explanation to provide

Approved explanation: In the Resources module, a value like 0.8H / 40.0H means 0.8 hours logged out of 40 available hours for that resource during the selected time period.

  • First value: actual work logged

  • Second value: total available capacity for the selected period

  • Scope: the logged time shown in this context applies to work items within the specific Program/Project (box) being viewed

  • Not instance-wide: this is not the user’s total logged time across the entire Jira instance

How to explain Team view

When the customer asks about Team view, explain that it shows the workload and total logged time for the entire team in the context of the currently viewed box.

  • It aggregates values from team members

  • It reflects work items assigned to those team members within the current box context

  • It should not be described as a global Jira-wide team timesheet unless documentation explicitly says so for that scenario

If the customer is comparing Team view with time tracking outside the box, remind them that the Resource module is context-sensitive and should be interpreted within the currently selected box and time period.

Recommended support reply

Hi [Customer Name],

Thank you for reaching out to BigPicture support.

In the Resources module, a value such as 0.8H / 40.0H means that 0.8 hours have been logged out of a total of 40 available hours for that resource in the selected time period.

The logged value shown there reflects time recorded for work items within the specific Program/Project (box) you are currently viewing, rather than all work items across the whole Jira instance.

In Team view, the module displays workload and total logged time for the entire team by aggregating the hours of team members for work items assigned to them within that same box context.

For more details, please refer to the documentation here: Capacity calculation.

Please note that we do not have access to customer instance data, so we can clarify product behavior but cannot inspect box contents directly.

Best,
Appfire Support

Suggested handling workflow

Confirm the question is about BigPicture Resources module calculations
Explain the meaning of the logged hours versus available hours format
Clarify that the calculation is box-contextual, not instance-wide
Explain Team view as aggregated team workload within the same box context
Share the capacity calculation documentation link
State clearly that Support cannot access the customer’s instance contents

Do and don’t guidance

Do

Don’t

Why it matters

Do

Don’t

Why it matters

Explain the value as logged time out of available capacity

Describe it as a generic progress percentage

Customers are asking about time-based calculation, not status tracking

Anchor the answer to the selected box and time period

Suggest the figure includes all Jira work by default

This prevents incorrect expectations about instance-wide totals

Describe Team view as aggregated team data in current context

Call it a universal team timesheet without qualification

Team totals depend on scope and viewed context

Link the documentation article

Rely only on a short custom explanation

The doc gives the customer a durable self-service reference

Common pitfalls

Avoid overcommitting on data visibility. If a customer shares a site link, do not imply Support can inspect their actual configuration or records unless access has been explicitly granted through an approved process.

  • Do not say values are Jira-instance-wide unless verified for the exact view and setup

  • Do not assume the customer understands that capacity depends on the selected period

  • Do not skip the documentation link when the customer explicitly asks for detailed material

Escalation guidance

Escalate or seek internal clarification if:

  • The customer reports numbers that appear inconsistent with the documented box context

  • The question involves unexpected calculation behavior rather than a usage explanation

  • The issue may depend on configuration, app version differences, or a possible defect