Understanding BigPicture Resources Module: Capacity and Team View Calculations
Use this guide when customers ask how BigPicture Resources values are calculated, especially entries such as 0.8H / 40.0H, team workload totals, and whether values apply to a specific box or the full Jira instance.
Best use case: Documentation-style support questions from evaluators or customers who want clarification on the Resources module behavior in BigPicture Cloud.
When to use this response pattern
Customer asks what the first value in a resource capacity display means
Customer wants to know whether logged time is calculated for the current Program/Project only or the whole Jira instance
Customer asks how Team view totals are calculated
Customer requests supporting documentation for the Resources module
Core explanation to provide
Approved explanation: In the Resources module, a value like 0.8H / 40.0H means 0.8 hours logged out of 40 available hours for that resource during the selected time period.
First value: actual work logged
Second value: total available capacity for the selected period
Scope: the logged time shown in this context applies to work items within the specific Program/Project (box) being viewed
Not instance-wide: this is not the user’s total logged time across the entire Jira instance
How to explain Team view
When the customer asks about Team view, explain that it shows the workload and total logged time for the entire team in the context of the currently viewed box.
It aggregates values from team members
It reflects work items assigned to those team members within the current box context
It should not be described as a global Jira-wide team timesheet unless documentation explicitly says so for that scenario
If the customer is comparing Team view with time tracking outside the box, remind them that the Resource module is context-sensitive and should be interpreted within the currently selected box and time period.
Recommended support reply
Hi [Customer Name],
Thank you for reaching out to BigPicture support.
In the Resources module, a value such as 0.8H / 40.0H means that 0.8 hours have been logged out of a total of 40 available hours for that resource in the selected time period.
The logged value shown there reflects time recorded for work items within the specific Program/Project (box) you are currently viewing, rather than all work items across the whole Jira instance.
In Team view, the module displays workload and total logged time for the entire team by aggregating the hours of team members for work items assigned to them within that same box context.
For more details, please refer to the documentation here: Capacity calculation.
Please note that we do not have access to customer instance data, so we can clarify product behavior but cannot inspect box contents directly.
Best,
Appfire Support
Suggested handling workflow
Do and don’t guidance
Do | Don’t | Why it matters |
|---|---|---|
Explain the value as logged time out of available capacity | Describe it as a generic progress percentage | Customers are asking about time-based calculation, not status tracking |
Anchor the answer to the selected box and time period | Suggest the figure includes all Jira work by default | This prevents incorrect expectations about instance-wide totals |
Describe Team view as aggregated team data in current context | Call it a universal team timesheet without qualification | Team totals depend on scope and viewed context |
Link the documentation article | Rely only on a short custom explanation | The doc gives the customer a durable self-service reference |
Common pitfalls
Avoid overcommitting on data visibility. If a customer shares a site link, do not imply Support can inspect their actual configuration or records unless access has been explicitly granted through an approved process.
Do not say values are Jira-instance-wide unless verified for the exact view and setup
Do not assume the customer understands that capacity depends on the selected period
Do not skip the documentation link when the customer explicitly asks for detailed material
Escalation guidance
Escalate or seek internal clarification if:
The customer reports numbers that appear inconsistent with the documented box context
The question involves unexpected calculation behavior rather than a usage explanation
The issue may depend on configuration, app version differences, or a possible defect