Guidance for Managing Workload and Time Tracking in BigPicture Standard
This page outlines the recommended support response for customers who want to compare resource planning with actual time spent in BigPicture Standard, especially when they ask about non-uniform workload distribution, visual deviation tracking, and past-versus-future workload behavior.
Use this article when a customer asks how to manage planning and execution in BigPicture Standard without relying heavily on external time-tracking apps, and whether Enterprise-only capabilities are required.
Problem
Customers may want to achieve all of the following in BigPicture Standard:
Plan resource allocation across tasks
Represent non-linear effort distribution during a task's duration
Log actual time spent and compare it with the plan
Spot when actuals exceed planned effort or when work is slipping
Show historical periods as actuals and future periods as planned workload
Adjust schedules automatically when remaining work increases
The key challenge is that some of these expectations are only partially supported in BigPicture Standard, while others require Enterprise features or external time-tracking integrations.
Short Answer
BigPicture Standard supports planning, schedule monitoring, baselines, and visual workload management, but it does not provide:
manual workload contouring across a single task
native built-in time tracking inside BigPicture
automatic threshold-based alerts when actual effort exceeds plan
automatic switching of past workload display to actuals while keeping future periods planned
If the customer specifically wants uneven effort allocation across one task or automatic historical actual-vs-future planned workload switching, set expectations clearly: these are not available in BigPicture Standard as described in this case.
Recommended Support Guidance
1. Non-uniform workload distribution across a task
In BigPicture Standard, workload is generally distributed evenly across the scheduled duration of the task. Since manual workload contouring is an Enterprise capability, the recommended workaround is to break work into smaller items.
Best practice: suggest splitting the task into sub-tasks or separate tasks that reflect the real effort pattern. This is the most precise workaround in Standard.
Example approach:
Create one sub-task for the high-effort period
Create another sub-task for the lighter-effort period
Assign each item its own duration, estimate, and assignee
Let the Resources module reflect allocation through those separate work items
This gives the customer a more realistic workload picture than keeping one long task with evenly spread effort.
2. Logging actual time spent
BigPicture does not include native time-tracking functionality for entering actual time directly inside the app. Actual time should be logged in Jira or via an integrated time-tracking solution.
Recommended options
Jira native time tracking: use Original Estimate, Remaining Estimate, and Time Spent
7pace Timetracker: a stronger option when the customer wants richer timesheet capabilities and a dedicated integration with BigPicture
Useful links:
3. Comparing planned workload with actuals
In Standard, this comparison is available indirectly rather than through one dedicated planned-versus-actual workload mode.
Support should guide customers to combine the following mechanisms:
Jira estimates and logged time to capture actual execution data
Task dates based on estimates so changing Remaining Estimate can shift task dates
Baselines to compare original and current schedule assumptions
Resources module to review over-allocation and workload pressure visually
This setup gives customers a practical planning-versus-execution workflow in Standard, even though it is not a true side-by-side actual-vs-planned historical workload model.
4. Visual indicators for slippage or overload
If a customer asks for red flags, deviation markers, or automatic schedule reactions, clarify what is and is not available.
Available visual cues in Standard:
over-allocation indicators in the Resources module
schedule movement when estimates and dates change
baseline comparison to identify drift from the original plan
progress and remaining estimate changes visible on tasks
Not available as described:
automatic alert rules triggered by effort thresholds
native warning logic such as “actual exceeded planned by X%”
automatic historical redistribution of workload bars based on logged time
When responding to customers, avoid overstating automation. In this scenario, the product highlights deviations mainly through visual planning artifacts, not rule-based alerting.
5. Past vs future workload display
This is the most important limitation to explain clearly.
In BigPicture Standard, the Resources module does not automatically switch:
past dates to show actual time spent
future dates to show planned workload
Instead, workload remains based on planned effort distributed across the task's scheduled duration. Logged time affects progress and remaining estimate, but it does not redraw past workload periods to match real historical daily effort.
There is no built-in Standard mode that automatically separates historical actual workload from future planned workload in the Resources view.
If Remaining Estimate is updated and task-date recalculation is enabled, future scheduling may shift. However, this is not the same as converting past planned allocation into actual historical effort bars.
What to Recommend to Customers
Use task splitting to model non-linear effort distribution
Use Jira native time tracking or (preferably) 7pace Timetracker for actual time logging
Enable Task dates based on estimates if they want schedule movement based on remaining work
Use Baselines to identify slippage against original plans
Review Resources for overload indicators and capacity issues
Set expectations that manual contouring and past-actual/future-planned switching are not supported in Standard
Suggested Response Template
Thank you for the detailed description of your workflow. In BigPicture Standard, the recommended approach is to split tasks into smaller items if you need non-uniform effort distribution, because manual workload contouring is an Enterprise capability. For actual time spent, BigPicture does not provide native time tracking, so actuals should be logged in Jira or with an integrated solution such as 7pace Timetracker. To compare plan and execution, we recommend using Jira estimates and logged time together with Task dates based on estimates, Baselines, and the Resources module. Please note that Standard does not automatically switch past workload to actuals while keeping future workload planned, and it does not provide automatic threshold-based alerts when actual effort exceeds the plan.
Support Notes
Be explicit about Standard limitations early in the reply
Offer a workable alternative instead of only saying “not supported”
Position Jira native tracking as the default answer
Mention 7pace when the customer wants stronger time-tracking capability integrated with BigPicture
Frame baselines and estimate-driven scheduling as the main tools for monitoring slippage