Guidance for Managing Workload and Time Tracking in BigPicture Standard

Guidance for Managing Workload and Time Tracking in BigPicture Standard

This page outlines the recommended support response for customers who want to compare resource planning with actual time spent in BigPicture Standard, especially when they ask about non-uniform workload distribution, visual deviation tracking, and past-versus-future workload behavior.

Use this article when a customer asks how to manage planning and execution in BigPicture Standard without relying heavily on external time-tracking apps, and whether Enterprise-only capabilities are required.

Problem

Customers may want to achieve all of the following in BigPicture Standard:

  • Plan resource allocation across tasks

  • Represent non-linear effort distribution during a task's duration

  • Log actual time spent and compare it with the plan

  • Spot when actuals exceed planned effort or when work is slipping

  • Show historical periods as actuals and future periods as planned workload

  • Adjust schedules automatically when remaining work increases

The key challenge is that some of these expectations are only partially supported in BigPicture Standard, while others require Enterprise features or external time-tracking integrations.

Short Answer

BigPicture Standard supports planning, schedule monitoring, baselines, and visual workload management, but it does not provide:

  • manual workload contouring across a single task

  • native built-in time tracking inside BigPicture

  • automatic threshold-based alerts when actual effort exceeds plan

  • automatic switching of past workload display to actuals while keeping future periods planned

If the customer specifically wants uneven effort allocation across one task or automatic historical actual-vs-future planned workload switching, set expectations clearly: these are not available in BigPicture Standard as described in this case.

Recommended Support Guidance

1. Non-uniform workload distribution across a task

In BigPicture Standard, workload is generally distributed evenly across the scheduled duration of the task. Since manual workload contouring is an Enterprise capability, the recommended workaround is to break work into smaller items.

Best practice: suggest splitting the task into sub-tasks or separate tasks that reflect the real effort pattern. This is the most precise workaround in Standard.

Example approach:

  • Create one sub-task for the high-effort period

  • Create another sub-task for the lighter-effort period

  • Assign each item its own duration, estimate, and assignee

  • Let the Resources module reflect allocation through those separate work items

This gives the customer a more realistic workload picture than keeping one long task with evenly spread effort.

2. Logging actual time spent

BigPicture does not include native time-tracking functionality for entering actual time directly inside the app. Actual time should be logged in Jira or via an integrated time-tracking solution.

Recommended options

  • Jira native time tracking: use Original Estimate, Remaining Estimate, and Time Spent

  • 7pace Timetracker: a stronger option when the customer wants richer timesheet capabilities and a dedicated integration with BigPicture

Useful links:

3. Comparing planned workload with actuals

In Standard, this comparison is available indirectly rather than through one dedicated planned-versus-actual workload mode.

Support should guide customers to combine the following mechanisms:

  • Jira estimates and logged time to capture actual execution data

  • Task dates based on estimates so changing Remaining Estimate can shift task dates

  • Baselines to compare original and current schedule assumptions

  • Resources module to review over-allocation and workload pressure visually

This setup gives customers a practical planning-versus-execution workflow in Standard, even though it is not a true side-by-side actual-vs-planned historical workload model.

4. Visual indicators for slippage or overload

If a customer asks for red flags, deviation markers, or automatic schedule reactions, clarify what is and is not available.

Available visual cues in Standard:

  • over-allocation indicators in the Resources module

  • schedule movement when estimates and dates change

  • baseline comparison to identify drift from the original plan

  • progress and remaining estimate changes visible on tasks

Not available as described:

  • automatic alert rules triggered by effort thresholds

  • native warning logic such as “actual exceeded planned by X%”

  • automatic historical redistribution of workload bars based on logged time

When responding to customers, avoid overstating automation. In this scenario, the product highlights deviations mainly through visual planning artifacts, not rule-based alerting.

5. Past vs future workload display

This is the most important limitation to explain clearly.

In BigPicture Standard, the Resources module does not automatically switch:

  • past dates to show actual time spent

  • future dates to show planned workload

Instead, workload remains based on planned effort distributed across the task's scheduled duration. Logged time affects progress and remaining estimate, but it does not redraw past workload periods to match real historical daily effort.

There is no built-in Standard mode that automatically separates historical actual workload from future planned workload in the Resources view.

If Remaining Estimate is updated and task-date recalculation is enabled, future scheduling may shift. However, this is not the same as converting past planned allocation into actual historical effort bars.

What to Recommend to Customers

  1. Use task splitting to model non-linear effort distribution

  2. Use Jira native time tracking or (preferably) 7pace Timetracker for actual time logging

  3. Enable Task dates based on estimates if they want schedule movement based on remaining work

  4. Use Baselines to identify slippage against original plans

  5. Review Resources for overload indicators and capacity issues

  6. Set expectations that manual contouring and past-actual/future-planned switching are not supported in Standard

Suggested Response Template

Thank you for the detailed description of your workflow. In BigPicture Standard, the recommended approach is to split tasks into smaller items if you need non-uniform effort distribution, because manual workload contouring is an Enterprise capability. For actual time spent, BigPicture does not provide native time tracking, so actuals should be logged in Jira or with an integrated solution such as 7pace Timetracker. To compare plan and execution, we recommend using Jira estimates and logged time together with Task dates based on estimates, Baselines, and the Resources module. Please note that Standard does not automatically switch past workload to actuals while keeping future workload planned, and it does not provide automatic threshold-based alerts when actual effort exceeds the plan.

Support Notes

  • Be explicit about Standard limitations early in the reply

  • Offer a workable alternative instead of only saying “not supported”

  • Position Jira native tracking as the default answer

  • Mention 7pace when the customer wants stronger time-tracking capability integrated with BigPicture

  • Frame baselines and estimate-driven scheduling as the main tools for monitoring slippage