Troubleshooting Weekend Scheduling Issues in BigPicture: Holiday and Workload Plan Insights
This article helps support teams troubleshoot cases where a user tries to schedule a task on Saturday or Sunday in BigPicture, but the date is automatically moved to Friday or Monday.
In BigPicture, weekend scheduling is controlled by a combination of Holiday Plans, Workload Plans, and the app setting that validates task periods against an assignee’s working days. A change in only one place is often not enough.
Problem
A customer reports that a task cannot be scheduled on a weekend, even though the user is expected to work on Saturdays and Sundays. When the task is moved to a weekend date, the system automatically shifts it back to the nearest weekday.
This usually appears in environments where:
A user has weekend availability as part of their role or shift pattern.
A Holiday Plan was updated, but weekend scheduling still fails.
The issue occurs in automatic scheduling modes, while manual scheduling may behave differently.
The customer assumes the setting should be applied per box or project, while the actual configuration is resource-based.
Root Cause Summary
The most common cause is a mismatch between calendar-style availability and actual workload capacity.
Holiday Plan controls whether a day is considered working or non-working from a calendar perspective.
Workload Plan controls whether the user has capacity on that day.
Scheduling mode determines whether BigPicture validates dates against availability and capacity.
Working-days validation setting can force task dates to respect each assignee’s individual working days.
If weekends are marked as working days in a Holiday Plan, but the assigned Workload Plan still gives the resource 0h capacity on weekends, automatic scheduling will still treat Saturday and Sunday as unavailable.
How to Diagnose the Issue
Confirm the scheduling behavior.
Check whether the task always snaps from Saturday or Sunday to Friday or Monday, and whether this happens for one issue, one user, or multiple users.Check the task’s scheduling mode.
Verify whether the task uses Auto, Auto Bottom-Up, or Manual scheduling. Automatic modes validate against availability; manual mode can allow dates that automatic modes reject.Review the assigned Holiday Plan.
Confirm that the user’s Holiday Plan marks weekends as working days when the business requires weekend work.Review the assigned Workload Plan.
Confirm that the same user has non-zero capacity on Saturdays and Sundays. This is a key validation point.Check whether assignee working days validation is enabled.
In similar cases, customers resolved the issue by enabling the option that makes task periods respect each individual assignee’s working days.Clarify configuration scope.
Make sure the customer understands that Workload and Holiday Plans are assigned to users/resources, not directly to a box.
Resolution
Use the following process to resolve the issue.
Enable validation based on individual working days if the customer expects tasks to follow each assignee’s own calendar.
Update or assign the correct Holiday Plan so weekends are marked as working days for the affected user.
Update or assign the correct Workload Plan so the user has actual weekend capacity greater than 0 hours.
Retest in the relevant scheduling mode.
If the task uses Auto or Auto Bottom-Up, confirm that the weekend now remains selectable. If needed, compare the result with Manual scheduling to validate whether availability checks were the blocker.Create a dedicated Workload Plan for weekend-working users if multiple resources share that schedule.
In the source case, the customer confirmed the issue was resolved after adjusting the app configuration so working days were validated by individual user settings.
What Support Should Communicate
The behavior is expected when weekend days are unavailable in either the Holiday Plan or the Workload Plan.
Holiday Plans alone do not guarantee schedulability; the Workload Plan must also provide capacity.
Automatic scheduling modes enforce availability rules more strictly than Manual scheduling.
Plans are assigned per resource, not per box.
Suggested Troubleshooting Checklist
Useful Questions to Ask the Customer
Does this happen for one task or all tasks in the box?
Does it affect one user only, or multiple users?
What scheduling mode is used on the task?
Can the user move the task to another weekday successfully?
Are there any task constraints or dependencies affecting the dates?
Can the customer share screenshots of both the Holiday Plan and the Workload Plan?