This FAQ summarizes the outcomes and guidance on exporting configurations and their application to projects using Project Configurator for Jira (Data Center).
Summary
Administrators often need to move configurations (e.g., issue types, statuses, workflows, priorities, schemes) between Jira instances. This FAQ clarifies:
Whether you can export configuration without selecting a project
What happens when you import configuration into a target instance with an existing project of the same name
How and when project-level associations are applied
Best practices and troubleshooting steps
FAQs
1. Can I export a specific configuration without selecting a project?
No. Selecting a project is mandatory for export. Project Configurator’s export operation requires a project context to determine which configuration objects to include and how they relate to each other.
Why is a project required? Projects provide a coherent configuration boundary that references schemes, workflows, screens, fields, and other objects. The export logic uses this boundary to build a consistent, importable package.
2. Which configuration items are included when exporting from a project?
When you export using a project as context, Project Configurator includes the configuration objects referenced by that project, for example:
Issue type scheme and the referenced issue types
Workflow scheme and referenced workflows and statuses
Screens, screen schemes, and field configurations as referenced
Priorities, resolutions, and other shared objects referenced by the project
The exact content depends on your export options and the project’s actual references. See the official use-cases and options below.
3. Can I directly assign/import a configuration package to a specific target project during import?
Not directly. The import process brings configuration objects into the target instance and attempts to match or add them. Associating those imported objects (e.g., schemes, workflows) to a particular project is a separate step and is not automatically forced to a given project by the import alone.
After import, explicitly link the desired schemes/workflow schemes to your target project via Jira administration if you need to “apply” the configuration to that project.
4. What happens if the target instance already has a project with the same name?
During import, Project Configurator attempts to match existing configuration objects. Behavior includes:
If a referenced configuration object already exists and matches, it will be reused.
If it does not exist, it will be created on the target instance.
The import does not forcibly rewire your target project’s associations; you may need to manually associate the newly imported schemes/workflow schemes to the target project after import.
5. Will “Complete Project” export automatically apply all settings to the target project on import?
No. Importing a package, even from a complete project export, primarily ensures the configuration objects exist in the target instance. You must still associate those objects (e.g., Issue Type Scheme, Workflow Scheme, Screen Scheme, Field Configuration Scheme) to the target project as needed.
Good to know: If the target project already uses matching objects, they’ll remain associated. If the imported package adds new objects, you can switch the project associations to those objects after verifying they imported as expected.
6. How can I “apply” imported configuration to a particular project?
After the import completes successfully:
Navigate to Project settings in the target instance.
Associate the desired schemes/workflow scheme that were brought in by the import package.
Confirm screens, fields, and permissions align with expectations.
This post-import association step is the mechanism to “apply” configuration to the project.
7. How do I verify what was imported and diagnose mismatches?
Use the following diagnostics if the target project does not reflect the expected configuration after import:
Check the History Log to see object matches/creations and warnings: History log
8. What if I only want to move global/shared objects (e.g., statuses, priorities) but not tie them to any specific project?
Use a project-based export to collect the related objects, import them, and then selectively associate them as needed in the target instance. Project Configurator doesn’t support a “no-project” export. If you require extremely granular, object-only migrations, consider:
Preparing a minimal “source” project configured to reference only the objects you want to transport
Exporting from that minimal project so the export contains just the targeted references
Importing to the target instance and then associating objects where desired
Best Practices
Use a minimal “transport” project to curate exactly which objects are exported.
Review and clean up unused objects before export to avoid importing unnecessary configuration.
Always validate the import with the History Log; fix warnings and repeats early.
Post-import, explicitly reassociate schemes/workflow schemes to the intended project.