 Problem

After the snapshot is deployed, there are 2 fields for the Epic Color: one using the UK-English format Epic Colour and the other using the US-English format Epic Color.

This is due to the different languages being used in the Jira instances(source and target),

 Solution

Workaround #1

If you are in the testing phase of the migration, do the following:

  1. Go to Deployment on the target instance and select New project or Merge project based on the desired action.

image-20260616-031318.png
  1. Go to Deployment on the target instance and select New project or Merge project based on the desired action.

image-20260616-031520.png
  1. In the Fields section, select the Epic Color field and map it to the correct field in the target instance by selecting -->M.

  2. In the screenshot below, the Epic Colour field is mapped to the Epic Color field — this is the reverse of the required mapping. Follow a similar approach to map the Epic Color field from the snapshot to the appropriate target field.

image-20260616-031736.png

Check this in a non-production environment before performing it in the production environment.

Workaround #2

If the field that should remain is "Epic Color," perform a bulk update on the affected issues as described in the following article: