Effort progress
Visit the Contextual reports page to learn about availability, permissions, and how to add reports to your view.
See the video below.
Effort progress
The Effort progress report visualizes the project's progress in terms of effort according to the following formula: timeSpent / (remainingEstimate + timeSpent).
This report displays three data points that summarize all tasks within the selected box.
Original Estimate (this data point is always colored 100% and shows only the value of the Original Estimate)
Time Spent (Formula of the blue bar indicating the progress of the Time Spent:
timeSpent / (remainingEstimate + timeSpent))Remaining Estimate (Formula of the blue bar indicating the remaining estimated effort in the project:
remaining estimate / (remainingEstimate + timeSpent))