Cost Variance
How does it work
Keeping your project's budget on track can be tricky, especially when plans change over time. Luckily, there's an easier way. With the simplified budget-setting feature, you can quickly set up a cost baseline and take snapshots along the way. This makes it simple to compare your original planned costs with your actual or current cost estimates. By regularly checking these baselines, program and portfolio managers can stay in control, spot issues early, and make smarter decisions from start to finish.
About the snapshots
Snapshots of the financial information are taken for the entire app (all boxes). The first snapshot you take automatically becomes the baseline.
Snapshots can be taken manually or automatically. The automatic frequency of snapshots is based on configuration.
Snapshots can be removed.
The baseline snapshot can be changed.
Limitations: You can keep up to 15 snapshots.
You can manage snapshots in the Financials section of the app Administration.
Security and access
Role | Cost variance tab access | Configuration access |
|---|---|---|
Financial Viewer |
|
|
Financial Admin | ||
Box Admin | ||
App Admin | ||
Jira Admin |
Cost variance tab
Availability
The Cost Variance tab is available ONLY in portfolio boxes.
How to access
In the Financials module:
Go to the Cost variance tab in the side panel.
How to interpret the data
The app compares each snapshot with the current data.
On the right, you see data from the selected snapshots. On the left, you see the current information based on project boxes in a portfolio.
Cost variance | Description |
|---|---|
Negative cost variance | Costs increased compared to the snapshot. |
Positive cost variance | Costs decreased compared to the snapshot. |
Grey icon without numbers | No discrepancy between the snapshot and current data. |
Select snapshots for cost variance calculation
You can select multiple snapshots for comparison.
Add snapshots to the view
In the Cost variance tab of the Financials module:
Click the plus button to open the view adjustment menu.
In the Snapshots to compare section, click Add snapshot to open the dropdown.
Select a snapshot from the list.
Remove snapshots from the view
In the Cost variance tab of the Financials module:
Click the plus button to adjust the view.
In the Snapshots to compare section, click the bin icon.
Configuration
Initial setup
To set a baseline:
Go to the Cost Variance tab in the side panel.
Click Configure.
Adjust the automation settings.
Take the first snapshot to establish the baseline.
How to access the configuration page
Snapshot information and automation settings can be found in App Administration > Financials tab > Baselines.
Automation settings
You can set up the app to take the snapshots automatically:
At the end of each quarter
At the start of each month
Never