OKRs as task structure builders
OKRs as task structure builders (old navigation)
If in your box you have:
OKRs with Jira work items linked to their respective KRs
or, only OKRs with no Jira work items linked to their respective KRs,
then, BigPicture can automatically build the task hierarchy based on the relationships between the Strategic themes/Objectives, Key Results, and the work items linked to them (if present). This can be done by activating the Objective & Key Result task structure builder.
Activate Objective & Key Result task structure
Operations on task structure builders require a Jira/App Admin role. Changing a structure builder in a box will change a task hierarchy.
Task structure builders can be configured on the box configuration page.
The Objective & Key Result builder is available as a built-in template on the Task structure page. Click the template tile to select it.
Under the Advanced Configuration tab, you can see that your task tree will be built according to the following hierarchy:
Objective and Key Result (Strategic Theme > Objective > Key Result) > Epic > Sub-tasks.
If your Objectives or sub-objectives have other Objectives as their parent(s), this relationship will also be reflected on the task tree in the Gantt module.
When you activate the Objectives & Key Results structure builder, the app will pull the Objectives and Key Results data from the respective fields in the OKR module. See the OKR fields vs Jira fields page for more information.
Limitations
Currently, the Objective & Key Result structure builder on Gantt only works with work items linked to a single Key Result.
If multiple work items are assigned to a Key Result, the task structure and aggregations will be incorrect.
If a work item is linked to multiple Key Results, it will be displayed only once on the Gantt chart.
This limitation does not prevent you from linking more than one work item to a Key Result in the OKR module.
The OKR structure builder is not available in the non-scope boxes.
Linked boxes are not displayed anywhere on Gantt.
OKRs as task structure builders (new navigation)
If in your box you have:
OKRs with Jira work items linked to their respective KRs
or, only OKRs with no Jira work items linked to their respective KRs,
then, BigPicture can automatically build the task hierarchy based on the relationships between the Strategic themes/Objectives, Key Results, and the work items linked to them (if present). This can be done by activating the Objective & Key Result task structure builder.
Activate Objective & Key Result task structure
Operations on task structure builders require a Jira/App Admin role. Changing a structure builder in a box will change a task hierarchy.
Task structure builders can be configured on the box configuration page.
The Objective & Key Result builder is available as a built-in template on the Task structure page. Click the template tile to select it.
Under the Advanced Configuration tab, you can see that your task tree will be built according to the following hierarchy:
Objective and Key Result (Strategic Theme > Objective > Key Result) > Epic > Sub-tasks.
If your Objectives or sub-objectives have other Objectives as their parent(s), this relationship will also be reflected on the task tree in the Gantt module.
When you activate the Objectives & Key Results structure builder, the app will pull the Objectives and Key Results data from the respective fields in the OKR module. See the OKR fields vs Jira fields page for more information.
Limitations
Currently, the Objective & Key Result structure builder on Gantt only works with work items linked to a single Key Result.
If multiple work items are assigned to a Key Result, the task structure and aggregations will be incorrect.
If a work item is linked to multiple Key Results, it will be displayed only once on the Gantt chart.
This limitation does not prevent you from linking more than one work item to a Key Result in the OKR module.
The OKR structure builder is not available in the non-scope boxes.
Linked boxes are not displayed anywhere on Gantt.