Parent task conflicts occur when a parent task cannot be recalculated due to a constraint, such as a blocking task (for example, a task in locked mode), a non-working day, or when you use the manual period mode.
See the video about parent task conflicts.
Show parent task conflicts
The warning is displayed as a yellow box with a dashed-line frame and shows the position of the parent tasks calculated based on their children.
Parent task conflicts do NOT consider tasks without start and end dates (tasks without dates are ignored by parent task conflicts).
Parent task conflicts consider tasks with a single date, using only the existing date.
For more details, see the table below.
| |
|---|
The child task has no dates, and the parent has no dates. | No parent task conflict |
The child task has no dates, but its parent has dates. | No parent task conflict |
The child task only has a start date, and this is within the parent dates. | No parent task conflict |
The child task only has a start date, and this is before the parent starts. | The parent task conflict is displayed |
The child task only has a start date, and this is after the parent ends. | The parent task conflict is displayed |
The child task only has an end date, and this is within the parent dates. | No parent task conflict |
The child task only has an end date, and this is before the parent starts. | The parent task conflict is displayed |
The child task only has an end date, and this is after the parent ends. | The parent task conflict is displayed |
The parent has only one date. | No parent task conflict |
The warning can only be displayed using the Gantt module. To show the warnings:
Click Indicators > Parent task conflicts.
Reschedule tasks manually
Parent tasks in manual mode can be manually rescheduled so the task period is calculated based on child tasks.
To reschedule the task manually, click on the task to show the task’s details and click Reschedule.
Bulk rescheduling
Switch to one of the auto-scheduling modes to fix all the warnings.