Basic tasks / BigPicture tasks

Basic tasks have been renamed to BigPicture tasks as part of the new navigation rollout.

Both names refer to the same functionality. You may see either term depending on whether you’re using the previous navigation or the new navigation that is currently being rolled out in BigPicture.

Basic tasks (old navigation)

Basic tasks are stored by the App and are NOT synchronized with Jira or other connected tools like Trello. They can be viewed only using the App's Gantt, Scope, Board modules, or the WBS Widget.

They can coexist with other tasks and work great as placeholders or temporary tasks, and simulate higher levels in the hierarchy or serve as additional information boxes. The App uses them to replace non-issue Jira entities (like Components, Versions, Projects,) which it is unable to recreate in Jira while cloning the scope.

See the video about basic tasks below.

Scheduling

Basic tasks follow the same set of rules (including linking, sorting, etc.). However, dependencies (links) between basic tasks will not be synchronized. As basic tasks are not Jira issues, they do not use Jira fields, hence no dates are set as Start or End dates.

However, it is possible to aggregate the MIN (earliest) or MAX (latest) date from all the children's tasks by editing the Column Views, converting tasks to Milestone, and setting Baselines just like with other tasks. You can also manually color-code your basic tasks and multiple tasks using Task templates

Common use cases

As basic tasks are not stored in the Host Platform (in Jira) you can use them in a variety of ways. You can, for example:

  • convert them to milestones

  • convert them to Jira issues

  • use basic tasks as placeholders

  • use basic tasks as additional notes

  • use basic tasks to create a custom hierarchy and aggregate data

Convert a basic task into a Jira issue and select the issue type

  1. Right-click on the issue in the WBS and select Convert to Jira issue.

  2. Select a project in which a Jira issue will be created.

  3. Select Issue type (Task, Story, Bug, or Epic, etc.) to a Jira issue that will be created.

convert.png
  1. The Jira issue creation dialog will appear. Fill out and modify the issue fields. Once you're done, click Create.

image-20250324-130317.png

If the Jira issue's screen scheme does not contain some of the basic task fields, their field values will be lost after the conversion.

For example, if you have set an "original estimate" for a basic task, but the project in which you want to place a Jira issue doesn't allow for the use of the "original estimate" field, the app doesn't have a place to save the values. 

If you convert a basic task into a Jira issue, values that can't be saved are lost. 

  1. In place of a basic task you will see a Jira issue

Create a basic task

  1. Click the (plus icon) > Create task basic task

  2. Fill in the task information. It is not mandatory to add Start date and End date.

  3. Click Create 

Create another

When the box is selected → after you click Create a new task creation box automatically appears. 

Basic task statuses

basic tasks can have three statuses to choose from:

  • To-do

  • In progress

  • Done

Keyboard shortcut

  1. Select a task on WBS (task tree on the left)

  2. Use the shortcut to open the 'task creation box 

Create as a milestone

To create a milestone, activate a toggle switch. 

image-20250324-130422.png

Task structure based on basic tasks

Building the task structure using the basic task can only be done manually using drag & drop or indent/outdent arrows. 

Basic tasks templates

basic tasks can be arranged into Templates. Use this to add multiple tasks that represent repeatable items, such as project phases.

Assignee

Basic tasks can be assigned to users in the Resources module. To assign a task use the drag-and-drop mechanism. (You can also add the Assignee column in the Gantt module and then edit the fields in this column - it works for the Assignee field, not Jira Assignee).

The built-in assignee field will correctly display the assignment in other modules (in the Gantt module you can also use this field to assign a user to a basic task).

Assign team to basic tasks

It is possible to quickly assign a given Team to basic tasks by inline editing in a column view.

Workload of basic tasks

In the "Manual" workload contouring mode, you can assign workload to basic tasks. It will be accounted for in the general capacity calculation in the same manner as all other tasks. 

Limitations

Task reports 

Task reports cannot be created for basic tasks. 

BigPicture tasks (new navigation)

BigPicture tasks are stored by the App and are NOT synchronized with Jira or other connected tools, such as Trello. They can be viewed only using the Gantt, Scope, Board modules, or the WBS Widget.

They can coexist with other tasks and work great as placeholders or temporary tasks, and simulate higher levels in the hierarchy or serve as additional information boxes. 

See the video about BigPicture tasks below.

Scheduling

BigPicture tasks follow the same set of rules (including linking, sorting, etc.). However, dependencies (links) between BigPicture tasks will not be synchronized. As BigPicture tasks are not Jira work items, they do not use Jira fields, and no start or end dates are set.

However, it is possible to aggregate the MIN (earliest) or MAX (latest) date across all the children's tasks by editing the column views, converting tasks to milestones, and setting baselines just like with other tasks. You can also manually color-code your BigPicture tasks and multiple tasks using task templates.

Common use cases

Since BigPicture tasks are not stored in the host platform (Jira), you can use them in a variety of ways. You can, for example:

  • Convert them to milestones

  • Convert them to Jira work items

  • Use BigPicture tasks as placeholders

  • Use BigPicture tasks as additional notes

  • Use BigPicture tasks to create a custom hierarchy and aggregate data

Convert a BigPicture task into a Jira iwork item and select the work item type

  1. Right-click on the BigPicture task in the WBS and select Convert to Jira issue.

    Screenshot of the Convert to Jira issue button.
  2. Select a Jira space and work item type.

    Screenshot of the Convert BigPicture task to Jira issue window.
  3. The Jira work item creation dialog will appear. Fill out and modify the fields. Once you're done, click Create.

    Screenshot of the Jira work item creation dialog.

If the Jira work item's screen scheme does not include some of the BigPicture task fields, their field values will be lost during conversion.

For example, if you have set an "original estimate" for a BigPicture task, but the space where you want to place a Jira work item doesn't support the "original estimate" field, the app doesn't have a place to save the value. 

If you convert a BigPicture task into a Jira work item, values that can't be saved are lost. 

Screenshot of an example when Jira work item's screen scheme doesn't include some of the BigPicture task fields.
  1. In place of a BigPicture task, you will see a Jira work item.

    Screenshot of the converted BigPicture task to a Jira work item.

Create a BigPicture task

  1. Click Tasks > Create BigPicture task.

    Screenshot of the Create BigPicture task feature in the Gantt module.
  2. Fill in the task information. It is not mandatory to add the start date and end dates.

    Screenshot of the Create BigPicture task dialog.
  3. Click Create BigPicture task.

Create another

When the Create another box is selected, and you click Create BigPicture task, a new task creation window automatically appears. 

Screenshot of the Create BigPicture task dialog with the Create another box checked.

BigPicture task statuses

BigPicture tasks can have three statuses to choose from:

  • To Do

  • In progress

  • Done

Screenshot of the available BigPicture task statuses.

Keyboard shortcut

  1. Select a task on the WBS (task tree on the left).

  2. Use the shortcut to open the BigPicture task creation window.

    Screenshot of the keyboard shortcuts for BigPicture tasks.

Create as a milestone

To create a milestone, toggle the switch. 

Screenshot of the Create BigPicture task dialog with the Create as a milestone toggle switched.

Task structure based on BigPicture tasks

Building the task structure using the BigPicture task can only be done manually using drag & drop or indent/outdent arrows. 

BigPicture tasks templates

BigPicture tasks can be arranged into templates. Use this to add multiple tasks that represent repeatable items, such as project phases.

Assignee

BigPicture tasks can be assigned to users in the Resources module. To assign a task, use the drag-and-drop mechanism. You can also add the Assignee column in the Gantt module and then edit the fields in this column - it works for the Assignee field, not Jira Assignee.

Video presenting how to drag and drop a task to assign it to a user in the Resources module.

The built-in assignee field will correctly display the assignment in other modules (in the Gantt module, you can also use this field to assign a user to a BigPicture task).

Assign team to BigPicture tasks

It is possible to quickly assign a given team to BigPicture tasks by inline editing in a column view.

Screenshot of the Team column added to the Gantt column view.

Workload of BigPicture tasks

In the "Manual" workload contouring mode, you can assign workload to BigPicture tasks. It will be accounted for in the general capacity calculation in the same manner as all other tasks. 

Screenshot of a BigPicture task with the Manual contouring mode selected.

Limitations

Task reports 

Task reports cannot be created for BigPicture tasks. 

 

Need support? Create a request with our support team.